# 319 Fifth St, Jersey City

Condominium · 2 units · built 2024 · Block 11208, Lot 13.

On Umarelli: https://umarelli.org/jersey-city/11208/13/319-fifth-st

More construction in Harsimus Cove: https://umarelli.org/jersey-city/downtown/harsimus-cove.md

## Building permits

- New, issued Mar 4, 2022, estimated cost $855K, 2 units, 3 stories
- Alteration, issued Apr 4, 2024, estimated cost $10K, described as “Update and Planning approval to Tear down leaning building facade on existing renovation project and reframe.”
- Alteration — Residential, issued Feb 2, 2022, estimated cost $20K
- Alteration — Residential, issued Nov 1, 2021, estimated cost $3K
- Alteration, issued Oct 31, 2017, described as “Installation of rooftop solar PV system”
- Alteration, issued May 17, 2017, described as “Re Roof torch down”
- Alteration, issued May 18, 2007, described as “Brick veneer siding over existing brick facade new stair treads to front door”
- Alteration, issued Oct 17, 2005, described as “Replace old wood shingles with new wood shingles”

## Property taxes

- Assessment: $3,245,500
- 2023 tax: $24,861
- Assessed land: $1,298,300
- Assessed improvements: $2,781,800
- Exemptions and abatements: $834,600
- Condo units with their own tax lots: 2

## Zoning

RC-3 (Residential Commercial District 3).

## Recent sales

- Feb 28, 2025: $2,150,000, Unit 0002, 2,904 sq ft ($740 per sq ft)
- Sep 19, 2024: $2,335,000, 2,850 sq ft ($819 per sq ft)
- Oct 7, 2020: $1,200,000, 1,420 sq ft, sold with other lots

Open-market sales since mid-2019, from the state’s SR1A sales file.

## Flood zone

Current FEMA flood map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 9 ft (NAVD88). FEMA’s preliminary map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 11 ft (NAVD88).

## Board and land use applications

- Planning Board case P2023-0040: Site Plan Amendment, Approved, applied Jul 27, 2023. During the alteration of the existing facade it was determined that the framing is deteriorated/rotted and needs to be replaced. There are layers of non original shake siding and foam insulation over the original clapboard siding which…

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology