80 West Street, Manhattan
Hotel · built 1989 · Block 55, Lot 16.
Building permits
- Alteration, filed Aug 19, 2026, described as “IRA to assist with Condition Assessment”
- Alteration, filed Jan 15, 2026, estimated cost $1K, described as “Plumbing scope of work is for kitchen gas shutoff valve. Filed in conjunction with FDNY fire surpression job # 2025-tmrghd-004512-plan. No change to use, egress or occupancy.”
- Alteration, filed Jul 2, 2025, estimated cost $50K, described as “Install permanent channels on building facade for flood barrier system. No change to use egress or occupancy on this application.”
- Alteration, filed Sep 22, 2024, described as “Material hoist”
- Alteration, filed May 5, 2023, estimated cost $40K, described as “Partial removal of existing wall and rolling door, and replace with installation of a rated partition a fire rated rolling door, and patching of existing waterproofing floor to match existing, no change to use ,egrass, or occupancy.”
- Alteration, filed Dec 28, 2021, described as “Sidewalk shed”
- Alteration, filed Feb 8, 2021, estimated cost $399K, described as “Installation of mechanical system, air handler, condensing units & related duct work as shown on drawings. No change to use, egress or occupancy.”
- Alteration, filed Oct 19, 2020, estimated cost $5K, described as “Modification to existing sprinkler system and related piping. Relocate 6 sprinkler heads as shown on drawings. No change to ues egress or occupancy.”
- Alteration, filed Sep 30, 2019, estimated cost $5K, described as “Illuminated non advertising accessory wall sign - marriott. No change to use, egress or occupancy.”
- Alteration, filed Sep 30, 2019, estimated cost $5K, described as “Illuminated non advertising accessory wall sign - marriott. No change to use, egress or occupancy.”
Property taxes
- Assessment
- $47,078,550
- 2026–27 tax
- $4,801,143
- Market value (city estimate)
- $104,619,000
- Taxable value
- $44,258,321
- Assessed land
- $18,000,000
- Assessed improvements
- $29,078,550
Zoning
C6-9: floor area ratio 20.85 built, above the 15.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 10 ft (NGVD29). FEMA’s preliminary map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 11 ft (NAVD88).
Board and land use applications
- ROY'S (City Planning P2002M0646): Completed, decided Jun 10, 2002. RENEWAL-UNENCLOSED SIDEWALK CAFE FOR 5-YEARS, WITH 26 SEATS; Additional Other #(s): A11029260
- MARRIOTT FINANCIAL (City Planning P2000M0614): Completed, decided Sep 6, 2000. NEW-UNENCLOSED SIDEWALK CAFE, WITH 26 SEATS
- MARRIOTT FINANCIAL CENTER HOTEL (City Planning P1992M0058): Completed, decided Sep 10, 1991. FOLLOW-UP ALLOWING FOR THE COMPLETION OF THE RECTOR ST SUB-*WAY IMPROVEMENT WITHIN THE SPECIAL GREENWICH ST DIST
- MARRIOT FINANCIAL CENTER HOTEL (City Planning P1990M0467): Completed, decided Nov 14, 1990. FOLLOW-UP FOR CHAIRPERSON TO FIND EXISTENCE OF A FORCE*MAJEURE EVENT TO DELAY THE SUBSTANTIAL COMPLETION OF RECTOR*STREET SUBWAY IMPROVEMENT IN THE SPECIAL GREENWICH ST DIST
- LE MERIDIEN LIBERTY HOTEL (City Planning P1988M0303): Completed, decided Feb 24, 1988. CHAIRPERSON'S CERT TO OBTAIN AN ADDITIONAL 129,000SF OF*ZONING FLOOR AREA TO BUILD A HOTEL IN THE SPECIAL GREENWICH*STREET DISTRICT