21 Dey Street, Manhattan
Museum · built c. 1935 · Block 63, Lot 6.
Building permits
- No Work, filed Oct 23, 2026, described as “Temporary event ' I have a Secret to Share With You"”
- Alteration, filed May 28, 2025, estimated cost $105K, described as “Filing to add sprinkler booster pump to schedule B. Pump was filed and approved under application #M00783193. No change in use, egress or occupancy.”
- Alteration, filed Sep 10, 2024, estimated cost $165K, described as “Remove existing air handling units, associated piping and ductwork branches. Provide and install new vrf systems, new energy recovery ventilators, and new split system for 1ST floor lobby.”
- No Work, filed Oct 25, 2023, described as “Requesting TPA at 1st and 2nd floor for assembly gathering from 12/26/23 to 3/25/24 for 90 days, times 10am to 10pm and 9 FGs to be provided. (1st flr, 518 persons w/6FGs & 2nd flr , 240 persons w/3 FGs.) Total occupancy, 758.”
- No Work, filed Oct 25, 2023, described as “Requesting TPA for 90 days in an assembly space from 12/26/23 to 3/25//24 from 10am to 10pm. 3 FGs to be provided.”
- Alteration, filed Oct 3, 2023, estimated cost $5K, described as “Installation of construction fence as per plans. Construction fence shall comply with chapter #33 of the 2022 code no change in use, egress or occupancy under this application.”
- No Work, filed Jul 13, 2023
- No Work, filed Jul 13, 2023
- Alteration, filed Aug 30, 2022, estimated cost $115K, described as “Alteration of existing sprinkler system as shown on plans”
- Alteration, filed Aug 30, 2022, estimated cost $850K, described as “Installation of mechanical equipment and ductwork as shown on plans”
- Alteration, filed Aug 30, 2022, estimated cost $285K, described as “Installation of plumbing fixtures and piping at cellar and 1st floor as shown on plans”
- Alteration, filed Aug 10, 2022, estimated cost $250K, described as “Interior general construction work to commercial spaces at cellar, 1st, 2nd, and 3rd floors”
- Alteration, filed Jul 11, 2022, estimated cost $25K, described as “Removal of sprinkler heads and installation of temporary core sprinkler protection”
- Alteration, filed Jun 14, 2022, estimated cost $103K, described as “Structural work as shown on plans”
- Alteration, filed Dec 27, 2021, estimated cost $50K, described as “Remove all non-load bearing partitions on the cellar floor through third floor. no chance of use egress or occupancy. Application Filed in conjunction with ALT CO # M00622953-I1.”
- Alteration, filed Nov 5, 2021, estimated cost $250K, described as “Convert cellar, 1st, and 2nd floors to UG 10 studio with accessory office and storage spaces on 3rd floor. Construct new egress stair at cellar, 1st, 2nd, 3rd, and 4th floors.”
Property taxes
- Assessment
- $8,486,100
- 2026–27 tax
- $842,958
- Market value (city estimate)
- $18,858,000
- Taxable value
- $7,770,628
- Assessed land
- $2,443,500
- Assessed improvements
- $6,042,600
Zoning
C5-5: floor area ratio 3.97 built, 15.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- Change to an earlier grant (Board of Standards and Appeals 331-04-BZII): Change to an earlier grant, Granted, filed Oct 24, 2013, decided Mar 11, 2014. Amendment of a previously approved Variance (§72-21) which permitted the expansion of floor area in an existing commercial structure (Century 21). The amendment seeks to permit a rooftop addition above the existing building which exceeds…
- Variance or special permit (Board of Standards and Appeals 331-04-BZ): Variance or special permit, Granted, filed Oct 7, 2004, decided Feb 15, 2005. Variance (§72-21) to permit in a C5-5 (Lower Manhattan Special District) the expansion of floor area in an existing commercial structure (Century 21). The proposed enlargement exceeds the maximum floor area permitted.
- LOWER MANHATTAN LOADING BERTH WAIVE (City Planning P2011M0185): Completed, decided Nov 20, 2012. 11DCP133M: AMENDMENT TO SECTION 91-50 FO THE NYCZR TO CREATE A NEW CPC CHAIR CERT. TO WAIVE OFF-STREET LOADING BETH REQUIREMENTS, A ND TO APPLY FOR A CERT. UNDER THE NEW TEXT