# 215 Pearl Street, Manhattan

Hotel · built 2015 · Block 69, Lot 1.

On Umarelli: https://umarelli.org/nyc/1000690001/215-pearl-street

More construction in Financial District: https://umarelli.org/nyc/manhattan/financial-district.md

Every lot on block 69: https://umarelli.org/nyc/manhattan/69.md

## Building permits

- No Work, filed Aug 4, 2025
- Alteration, filed Aug 4, 2025, described as “FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola”
- Alteration, filed Feb 7, 2025, estimated cost $83K, described as “Carrier: VZW. New Antenna Installation. Installing (3) new antenna sectors consisting of (9) antennas, (12) RRH Units, (3) OVP boxes, and (3) GPS on the roof. Install (3) equipment cabinets on new platform on roof. All work in conformance…”
- Alteration, filed Mar 8, 2024, estimated cost $5K, described as “File plumbing work to add one gas meter on cellar for the laundry rooms. No change of use, egress or occupancy.”
- Alteration, filed Dec 26, 2023, estimated cost $5K, described as “Erect non-flashing illuminated non-advertising wall sign for existing first and second floor eating and drinking establishment. Copy reading chinese characters and "yao" "bar & restaurant". No change of use, egress or occupancy.”
- Alteration, filed Jun 9, 2023, estimated cost $19K, described as “Modification of existing sprinkler system for the first and second floor eating and drinking establishment in conjunction with application# M00856816 and application# M00835322. No change of use, egress or occupancy.”
- Alteration, filed Apr 17, 2023, estimated cost $5K, described as “File temporary construction fence in conjunction to department of buildings application# M00856816. No change of use, egress or occupancy.”
- Alteration, filed Apr 17, 2023, estimated cost $5K, described as “File plumbing work to install one new hand sink only on first floor receptionist area in conjunction to department of buildings application# M00856816. No change of use, egress or occupancy.”
- Alteration, filed Apr 10, 2023, estimated cost $118K, described as “Interior renovation with partition works and new suspended ceiling, relocate stairway up to lobby. Install new storefront with new glass double doors. No change of use, egress or occupancy.”
- Alteration, filed Mar 17, 2023, estimated cost $34K, described as “File plumbing work in conjunction to department of buildings application# M00835322. No change of use, egress or occupancy.”
- Alteration, filed Mar 3, 2023, estimated cost $180K, described as “Job filed for interior renovation of a comm. Space u.g. 6 on 1ST floor , incl. New non-load-bearing partitions, kitchen millwork, and finishes as per plans. No change of use, egress or occupancy.”
- Alteration, filed Feb 28, 2023, estimated cost $150K, described as “Interior renovation with partition works, replace partial existing carpet with tile floor on second floor existing eating and drinking establishment. No change of use, egress or occupancy.”
- Alteration, filed Nov 3, 2021, estimated cost $1K, described as “Installation of roof protection for adjacent property during construction. Roof protection shall comply with nycc 2014 chapter 33 . No change in egress, use, or occupancy.”
- Alteration, filed Jul 20, 2021, described as “Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed May 10, 2021, estimated cost $250K, described as “Emergency stucco facade stabilization and make safe repairs as shown on drawings. No chanege to use, egress or occupancy.”
- Alteration, filed May 10, 2021, estimated cost $2.0M, described as “Stucco replacement as shown on drawings. No change to use, egress or occupancy”
- Alteration, filed Feb 26, 2019, estimated cost $3K, described as “Install Non-illuminated Wall Sign (Courtyard by Marriott - Residence Inn by Marriott)”

## Building history

- New Building — Tower, filed Mar 21, 2012, permit issued - entire job/work, 326 units, 38 stories
- New Building — High-Rise, filed Mar 2, 2007, plan exam - disapproved, 52 stories

New buildings, demolitions and major alterations filed in the city’s older system since 1989.

## Property taxes

- Assessment: $24,851,700
- 2026–27 Tax: $2,376,172
- Market value (city estimate): $55,226,000
- Taxable value: $21,882,055
- Assessed land: $1,145,250
- Assessed improvements: $23,706,450

## Zoning

C5-5: floor area ratio 23.70 built, above the 15.00 base zoning allows, which bonuses, transfers or older rules can permit.

## Flood zone

Current FEMA flood map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 10 ft (NGVD29). FEMA’s preliminary map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 11 ft (NAVD88).

## Board and land use applications

- 2 Gold St Café re-cert POPS (City Planning P2012M0579): Completed, decided Aug 17, 2012. Chairperson certification for an open air café within an existing urban plaza.
- PLAZA & CAFE (City Planning P2007M0156): Completed, decided Feb 1, 2007. CERT TO EXPAND AN EXISTING URBAN PLAZA WITHIN THE SPECIAL\*LOWER MANHATTAN DIST (POPS)
- PLAZA & CAFE (City Planning P2006M0433): Completed, decided Aug 15, 2006. CERT FOR COMPLIANCE WITH THE REQUIREMENTS FOR AN URBAN PLAZA\*(POPS)
- 2 Gold Street Cafe Certification (City Planning P2018M0168): Certification, Filed. A private application seeking a certification for an open air cafe (37-73) within a Plaza located at 2 Gold Street. The last certification took place in 2012, expired in 2015)

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology