33 Park Row, Manhattan
Condominium · 30 units · built 2016 · Block 90, Lot 7505.
Building permits
- Alteration, filed Oct 20, 2026, described as “Installation of suspended scaffold for facade inspection/repair.”
- Alteration, filed Feb 27, 2026, estimated cost $400K, described as “Filing herewith removal of existing toilet room; all fixtures to be capped. New partitions and cabinetry. No change to use, occupancy or egress”
- Alteration, filed Sep 19, 2025, described as “FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS SEE ATTACHED PLANS Designated Primary Site supervisor: Jesus Decola”
- Alteration, filed Aug 17, 2022, estimated cost $15K, described as “Modifications to existing Mechanical system ductwork, diffusers and fans related to apt. PH2(20th fl.) renovation.”
- Alteration, filed Aug 17, 2022, estimated cost $20K, described as “Remove and install plumbing fixtures & piping related to apt. PH2 (20th fl.) renovation.”
- Alteration, filed Aug 12, 2022, estimated cost $275K, described as “Remove and install interior non load bearing partitions and hung ceilings related to apt. PH2 (20th fl.) renovation.”
- Alteration, filed Jul 14, 2022, estimated cost $47K, described as “Mechanical Modifications to include relocation of existing AC Unit and rerouting of ductwork as required for New Stair Opening in apt. PH1”
- Alteration, filed Jul 5, 2022, estimated cost $290K, described as “Installation of convenient stair bet. 21st and 22nd floors, minor interior demo to create opening for new stair in apt. PH1”
- Alteration, filed Jun 22, 2022, estimated cost $91K, described as “Structural reinforcements and framing for new stair opening and stair bet. 21st and 22nd fl. in apt. PH1”
- Alteration, filed Jun 13, 2022, estimated cost $13K, described as “Installation of sprinkler heads & piping related to new stair renovation in APT PH1.”
- Alteration, filed Dec 18, 2021, estimated cost $50K, described as “Mechanical Modifications to include HVAC relocation and replacement of associated ductwork related to Cellar Amenity Space.”
- Alteration, filed Dec 17, 2021, estimated cost $100K, described as “Demolish and Install interior non-load bearing partitions and doors in the Cellar, installation of lighting fixtures and finishes on Roof Deck related to Amenity spaces”
- Alteration, filed Dec 16, 2021, estimated cost $60K, described as “Install plumbing fixtures and piping in the Cellar and Roof Deck.”
- Alteration, filed Sep 16, 2021, estimated cost $4K, described as “Modifications to sprinkler system”
- Alteration, filed Sep 1, 2021, estimated cost $114K, described as “Remove and Install interior non-load bearing partitions, shaft wall, doors, ceilings, millwork, finishes, New Structural infill and reinforcements in location of removed shaft related to Amenity spaces per plans filed.”
- Alteration, filed Apr 7, 2021, described as “Sidewalk shed proposed installation of sidewalk shed as per plan. No change in use,egress or occupancy.”
- Alteration, filed Oct 7, 2020, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jun 26, 2020, described as “Pipe scaffold proposed installation of pipe scaffold as per plan. No change in use,egress or occupancy.”
- Alteration, filed Oct 15, 2018, described as “Installation of pipe scaffold on beam system as per plans. No change in use, egress or occupancy.”
Property taxes
- Assessment
- $13,038,572
- 2026–27 tax
- $1,474,748
- Market value (city estimate)
- $28,974,598
- Taxable value
- $12,225,033
- Assessed land
- $520,202
- Assessed improvements
- $12,518,370
- Condo units with their own tax lots
- 34
Zoning
C5-5: floor area ratio 13.80 built, 15.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Recent sales
- Mar 13, 2026: $4,200,000, Apt 18B
- Dec 16, 2025: $18,500,000, Apt PH3
- Nov 25, 2025: $5,625,000, Apt 15A
- Oct 14, 2025: $4,700,000, Apt 17B
- May 5, 2025: $4,895,000, Apt 10A
- May 5, 2025: $2,700,000, Apt 10B
- Dec 30, 2024: $5,350,000, Apt 14A
- Dec 23, 2024: $2,705,000, Apt 11B
- Nov 6, 2024: $5,180,000, Apt 11A
- Oct 10, 2024: $1,760,000, Apt 8C
The 10 most recent of 28 open-market sales since 2016, from the Department of Finance’s sales files.
In the news
No. 33 Park Row Wraps Up Construction in Financial District, Manhattan, New York YIMBY, Aug 6, 2021.