101 Barclay Street, Manhattan
Commercial · built 1983 · Block 128, Lot 2.
Building permits
- Alteration, filed Nov 11, 2026, estimated cost $5K, described as “Interior renovation of cellar (A Level -BNY) removal of non-load bearing partitions, ceilings, and associated elements as per the plans. No change to use, egress, or occupancy.”
- Alteration, filed Oct 1, 2026, estimated cost $5K, described as “Installation and use of temporary mini crane construction equipment as per plans filed herewith.”
- Alteration, filed Sep 24, 2026, estimated cost $250K, described as “Modifications to the existing HVAC system, including the removals and ducts & piping on the 3rd & 4th Floors (BNY), as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Sep 24, 2026, estimated cost $100K, described as “Alteration of the existing sprinkler system on the 3rd & 4th Floors floor, including removal of heads and installation of a temp loop, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Sep 24, 2026, estimated cost $100K, described as “Interior modifications to the existing plumbing system, including removals of fixtures, on the 22nd Floor, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Sep 23, 2026, estimated cost $1.8M, described as “Minor Interior demolition and white box of existing office space, including removal of ceilings, doors, floors, and partitions on the 3rd & 4th Floors (BNY), as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Sep 8, 2026, estimated cost $5K, described as “Installation and use of temporary knuckle boom construction equipment as per plans filed herewith.”
- Alteration, filed Aug 4, 2026, estimated cost $1K, described as “Weather wall on floors 1 -23, as per plans. Filed and fees paid in conjunction with DOBNOW # M01308436-I1. No change to use, egress, or occupancy.”
- Alteration, filed Jul 28, 2026, estimated cost $55K, described as “Structural remediation and reinforcement of deteriorated steel beam end connections and repairs at underside of deteriorated slab, at the 1st floor Loading dock and Parking area, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Jul 27, 2026, estimated cost $4K, described as “Temporary scaffold stair tower as per drawings. Scaffold stair tower shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Jul 24, 2026, described as “Suspended scaffolding as per drawings during bldg alteration filed separately. Suspended scaffold shall comply with ch 33 of the NYC bc. No change in use, occupancy or egress under this application.”
- No Work, filed Jul 23, 2026, described as “Momentum GIW Conference”
- Alteration, filed Jul 13, 2026, estimated cost $40K, described as “Interior modifications to the existing plumbing, including installation of coffee bar and grease trap in the first floor lobby, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Jun 17, 2026, estimated cost $500K, described as “Demolish one (1) existing buried 15,000-gallon fuel oil tank and the associated piping extending from the tank to the building facade on Level 1. Install one (1) new buried 15,000-gallon fuel oil tank with associated piping, valves, at the…”
- Alteration, filed Jun 17, 2026, estimated cost $500K, described as “Demolish one (1) existing 15,000-gallon fuel oil tank & the associated piping extending from tank to the building facade on Level 1. Install one (1) new buried 15,000-gallon fuel oil tank with associated piping, valves, pumps, at Cellar…”
- Alteration, filed Jun 17, 2026, estimated cost $800K, described as “Demolish two (2) existing buried 15,000-gallon fuel oil tanks and the associated piping extending from the tanks to the building facade on Level 1.”
- Alteration, filed Jun 15, 2026, estimated cost $850K, described as “Installation of a new dedicated exhaust fan for a new fuel oil pump room and misc. valves & leak detection installed on cellar and 2nd floor as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Jun 15, 2026, estimated cost $68K, described as “Modifications to the existing Sprinkler system cellar floor, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed May 27, 2026, estimated cost $10K, described as “Modification to the existing standpipe system on the 22nd Floor, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed May 27, 2026, estimated cost $1.3M, described as “Modifications to the existing HVAC system, including installation of units and associated ducts & piping on the 22nd Floor (BNY), as per plans. No change to use, egress, or occupancy.”
- Alteration, filed May 27, 2026, estimated cost $150K, described as “Alteration of the existing sprinkler system on the 22nd floor, including replacement of heads and new sprinkler heads, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed May 27, 2026, estimated cost $65K, described as “Interior modifications to the existing plumbing system, including installation of new fixtures, on the 22nd Floor, as per plans. No change to use, egress, or occupancy.”
- Alteration, filed May 20, 2026, estimated cost $4.2M, described as “Interior renovation of existing office space, including installation of ceilings, doors, floors, partitions, and finishes on the 22nd Floor (BNY), as per plans. No change to use, egress, or occupancy.”
- Alteration, filed May 15, 2026, estimated cost $275K, described as “Minor Interior demolition and buildout of existing office space, including removal of ceilings, doors, floors, and partitions on the 20th Floor (BNY), as per plans. No change to use, egress, or occupancy.”
- No Work, filed May 15, 2026, described as “BNY Live”
166 more, older permits are in this building’s full list on the map.
Property taxes
- Assessment
- $108,099,450
- 2026–27 tax
- $11,336,923
- Market value (city estimate)
- $240,221,000
- Taxable value
- $104,507,036
- Assessed land
- $17,010,000
- Assessed improvements
- $91,089,450
Zoning
C6-4: floor area ratio 11.00 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, moderate risk: a 0.2% chance of flooding each year. FEMA’s preliminary map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 11 ft (NAVD88).
Recent sales
- Sep 26, 2018: $352,000,000
Open-market sales since 2016, from the Department of Finance’s sales files.
Board and land use applications
- 240 Greenwich Street Minor Modification (City Planning P2018M0057): Special permit, Completed, decided Feb 15, 2022. Private application by the Bank of New York Mellon for a modification to a special permit (C 800477 ZSM) to remove "public lobby" label from recorded ground floor plans and improve outdoor open space as a Publicly Accessible Area (PAA) at…
- LM Plaza Applicability Text Amendment (City Planning P2017M0129): Completed, decided Jul 26, 2017. Zoning text amendment to Section 91-24 affecting the applicability of the public plaza bonus for sites within 50' of designated streets in C6-4 districts within the Special Lower Manhattan District.
- IRVING TRUST PEDESTRIAN BRDG. (City Planning P1989M0538): Completed, decided Jun 26, 1990. 89-131M: PROPOSED MODIFICATION TO REPLACE THE PROPOSED PEDESTRAIN CONNECTION WITH STAIRCASE FROM THE 2ND FLOOR EAST SIDE OF 7 WTC BLDG. TO SIDEWALK.
- 7TH AMENDMENT WASHINGTON ST URP (City Planning P1989M0464): Completed, decided Feb 8, 1990. ELIMINATE THE NORTH-SOUTH PEDESTRIAN EASEMENT FROM PARCEL 6*& THE CREATION OF 5D FOR PUBLIC SCHOOL 234
- 7 WORLD TRADE CENTER (City Planning P1989M0547): Completed, decided Feb 8, 1990. 89-131M: PROPOSED MODIFICATION TO REPLACE THE PROPOSED PEDESTRAIN CONNECTION WITH STAIRCASE FROM THE 2ND FLOOR EAST SIDE OF 7 WTC BLDG. TO SIDEWALK.
- IRVING TRUST CO (City Planning P1984M0908): Completed, decided Jul 18, 1984. 1ST MOD TO SPEC PERM FOR BLDG IN WASHINGTON ST URA BY*SUBSTUT A ST LEVEL PEDSTRN EASEMNT THRU BLDG FOR A WKWY*(POPS)