90 Lafayette Street, Manhattan
Religious · built 1944 · Block 195, Lot 21.
Building permits
- Alteration, filed May 4, 2023, estimated cost $9K, described as “Proposed installation of heavy duty sidewalk shed as per plans. Live load 300 per square feet. Sidewalk shed shall comply with chapter # 33 of the 2014 code. No change in use occupancy or egress under this application.”
- Alteration, filed May 26, 2022, estimated cost $15K, described as “Proposed installation of heavy duty sidewalk shed as per plans. Live load 300 lbs per square feet. Sidewalk shed shall comply with chapter #33 of the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Aug 2, 2021, estimated cost $13K, described as “It is proposed to modify existing plumbing system remove existing plumbing fixtures and install new plumbing fixtures as shown on plans. Application filed in conjunction with ALT I # 120033132.”
- Alteration, filed Mar 29, 2021, estimated cost $2K, described as “Install storefront awning with non-illuminated copy reading "logo". Copy not to exceed 12 sq ft total. No change in use, egress or occupancy.”
- Alteration, filed Nov 22, 2019, estimated cost $41K, described as “Modification of existing sprinkler system on 2nd & 6th floors. Modification includes removal, relocation and installation of sprinkler heads as shown on plans.”
Property taxes
- Assessment
- $2,371,950
- Market value (city estimate)
- $5,271,000
- Taxable value
- $0
- Assessed land
- $289,350
- Assessed improvements
- $2,082,600
Tax breaks
- Nonprofit exemption (house of worship), with no end date, about $257,309 a year below the full tax.
Zoning
C6-2A: floor area ratio 6.01 built, 6.02 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard. FEMA’s preliminary map: zone X, moderate risk: a 0.2% chance of flooding each year.
Board and land use applications
- Change to an earlier grant (Board of Standards and Appeals 7-00-BZIV): Change to an earlier grant, Granted, filed Feb 18, 2009, decided Jun 8, 2010. Extension of Time to Complete Construction of a previously granted Variance (§72-21) for the enlargement of a UG3 non-profit homeless shelter (New York City Rescue Mission) which expired on March 11, 2009; waiver of the rules. C6-2A zoning…
- Change to an earlier grant (Board of Standards and Appeals 7-00-BZIII): Change to an earlier grant, Granted, filed Jul 26, 2007, decided Sep 11, 2007. Extension of Time to Complete Construction for a Variance previously granted on May 30, 2000 to permit within an M1-5 zoning district an enlargement to a UG3, non-profit homeless shelter for men, (New York City Rescue Mission) which…
- Change to an earlier grant (Board of Standards and Appeals 7-00-BZII): Change to an earlier grant, Granted, filed Mar 31, 2004, decided Aug 10, 2004. Extension of time to complete construction for a non-profit homeless shelter for men (Use Group 4), located in an M1-5 zoning district.
- Variance or special permit (Board of Standards and Appeals 7-00-BZ): Variance or special permit, Granted, filed Jan 20, 2000, decided May 30, 2000. Variance (§72-21) to permit within an MI-5 zoning district, the proposed enlargement to a non-profit homeless shelter for men (Use Group 3) contrary to Z.R. §§22-14, 43-43.
- NYC RESCUE MISSION (City Planning P2012M0262): Completed, decided Jan 11, 2013. Special permit for bulk waivers for community facility use as part of NYC rescue mission expansion.