180 Orchard Street, Manhattan
Condominium · built 2008 · Block 412, Lot 7501.
Building permits
- Alteration, filed Apr 25, 2024, described as “Rigging for Industrial Rope Access”
- No Work, filed Oct 31, 2023, described as “Corporate party”
- No Work, filed Oct 19, 2023, described as “Corporate Party”
- Alteration, filed Feb 13, 2023, estimated cost $5K, described as “Erect accessory business sign for 2ND street, no change in use, egress or occupancy.”
- Alteration, filed Jan 9, 2023, estimated cost $33K, described as “Modification to Plumbing and Sprinkler systems as per plans filed herewith. No change in use, occupancy or egress.”
- No Work, filed Dec 20, 2022
- Alteration, filed Dec 20, 2022, estimated cost $100K, described as “Interior renovation at 12TH floor with change in occupancy and use.”
- Alteration, filed Jun 7, 2022, estimated cost $4K, described as “Plumbing work as per plans filed herewith. no change to use, egress or occupancy.”
- Alteration, filed May 26, 2022, estimated cost $50K, described as “Installation of 4 HVAC units in retail space as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Feb 23, 2022, estimated cost $75K, described as “Installation of HVAC unit and relocation of mechanical equipment as per plans filed herewith in Retail Space 'C'. No vent work is proposed. No change to use, egress or occupancy.”
- Alteration, filed Feb 8, 2022, estimated cost $38K, described as “Mechanical work as per plans filed herewith. No Change to use, egress or occupancy”
- Alteration, filed Feb 7, 2022, estimated cost $289K, described as “Interior renovations as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Aug 24, 2021, estimated cost $113K, described as “Mechanical work that involves the heating and cooling of the first floor commercial space via existing water source heat pumps in association with the general renovation of this same space. No change to use, occupancy or egress.”
- Alteration, filed Aug 24, 2021, estimated cost $84K, described as “Plumbing and Sprinkler work in association with general renovation of this 1st floor commercial space. No change to use, occupancy or egress.”
- Alteration, filed Aug 16, 2021, estimated cost $282K, described as “Renovation of existing commercial retail space at the first floor. No change to use, occupancy or egress.”
- Alteration, filed Aug 2, 2021, estimated cost $85K, described as “Demolition and construction to combine retail spaces 1 & 2 to retail space 1 consisting of non-load bearing partitions, interior doors & finishes. Construct 2 hr rated vestibule/exit passageway in (new) retail space 2 to comply w exit…”
- Alteration, filed Jul 30, 2021, estimated cost $44K, described as “Mechanical work associated with retail space(s) as per plans filed herwith.”
- Alteration, filed Jul 30, 2021, estimated cost $23K, described as “Sprinkler and standpipe work as per plans filed in relation with retail space.”
Property taxes
- Assessment
- $34,537,144
- 2026–27 tax
- $3,023,893
- Market value (city estimate)
- $76,749,208
- Taxable value
- $27,875,123
- Assessed land
- $1,826,550
- Assessed improvements
- $32,710,594
- Condo units with their own tax lots
- 3
Zoning
C4-4A: floor area ratio 12.77 built, above the 4.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Recent sales
- Oct 10, 2018: $162,500,000, Unit HOTEL
- Jul 11, 2016: $25,250,000, Unit RT.
Open-market sales since 2016, from the Department of Finance’s sales files.
Board and land use applications
- Appeal (Board of Standards and Appeals 8-15-A): Appeal, Granted, filed Jan 15, 2015, decided Jun 16, 2015. BZY Minor Development (§11-332) to extend the time of construction for a minor development for a period of six months; Determination of common law vested rights. Building permit was obtained in 2005 and development was vested at date of…
- Extension to finish construction (Board of Standards and Appeals 7-15-BZY): Extension to finish construction, Granted, filed Jan 14, 2015, decided Jun 16, 2015. BZY Minor Development (§11-332) to extend the time of construction for a minor development for a period of six months; Determination of common law vested rights. Building permit was obtained in 2005 and development was vested at date of…
- Extension to finish construction (Board of Standards and Appeals 201-10-BZYII): Extension to finish construction, Granted, filed Jan 18, 2013, decided Mar 19, 2013. Extension of time to complete construction (§11-332) for an additional two years for a minor development, which will expire on March 15, 2013. C4-4A zoning district.
- Extension to finish construction (Board of Standards and Appeals 201-10-BZY): Extension to finish construction, Granted, filed Oct 29, 2010, decided Mar 15, 2011. Extension of time (§11-332) to complete construction of a minor development commenced under the prior C6-1 zoning district. C4-4A zoning district .
- 180 Orchard Street Public Parking Garage (City Planning P2012M0093): Completed, decided Apr 28, 2015. Special permit to develop an attended 99-space public parking garage in a partially constructed hotel.