# 80 1st Avenue, Manhattan

Co-op · 877 units · built 1962 · Block 432, Lot 1.

On Umarelli: https://umarelli.org/nyc/1004320001/80-1-avenue

More construction in East Village: https://umarelli.org/nyc/manhattan/east-village.md

Every lot on block 432: https://umarelli.org/nyc/manhattan/432.md

## Building permits

- Alteration, filed Jul 8, 2025, estimated cost $643K, described as “Filing to waterproof the existing roof membrane as per plans. Also replacing existing perimeter railings. No change in use, egress, or occupancy under this application.”
- Alteration, filed May 9, 2025, estimated cost $643K, described as “Filing to waterproof the existing roof membrane as per plans. Also replacing existing perimeter railings. No change in use, egress, or occupancy under this application.”
- Alteration, filed Mar 19, 2025, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Mar 19, 2025, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Mar 19, 2025, estimated cost $1K, described as “Installation of temporary barrier as per plans. No change in use, egress or occupancy shall comply with CHAPTER#33 of 2022 the ny building code.”
- Alteration, filed Mar 19, 2025, estimated cost $1K, described as “Installation of temporary barrier as per plans. No change in use, egress or occupancy shall comply with CHAPTER#33 of 2022 the ny building code.”
- Alteration, filed Mar 4, 2025, described as “Installation of suspended scaffold for facade work or inspection.”
- Alteration, filed Mar 4, 2025, described as “Installation of suspended scaffold for facade work or inspection.”
- Alteration, filed Jan 30, 2024, described as “Outriggers system installation, material hoist for inspection for facade repairs.”
- Alteration, filed Jan 30, 2024, described as “Outriggers system installation, material hoist for inspection for facade repairs.”
- Alteration, filed Jan 30, 2024, described as “Outriggers system installation, material hoist for inspection for facade repairs.”
- Alteration, filed Jan 29, 2024, described as “Outriggers system installation, material hoist for inspection for facade repairs.”
- Alteration, filed Jan 29, 2024, described as “Outriggers system installation, material hoist for inspection for facade repairs.”
- Alteration, filed Mar 12, 2019, estimated cost $25K, described as “Installation of temporary sidewalk shed as per plans submitted. Work shall comply with building codes 2014 chapter 33. No change in use, egress, or occupancy.”
- Alteration, filed Mar 12, 2019, estimated cost $25K, described as “Installation of temporary sidewalk shed as per plans submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress, or occupancy.”
- Alteration, filed Mar 12, 2019, estimated cost $25K, described as “Installation of temporary sidewalk shed as per plans submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress, or occupancy.”
- Alteration, filed Mar 12, 2019, estimated cost $25K, described as “Installation of temporary sidewalk shed as per plans submitted. Work shall comply with building codes 2014 chapter 33. No change in use, egress, or occupancy.”
- Alteration, filed Aug 30, 2018, estimated cost $15K, described as “Installation of temporary sidewalk shed as per plans submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress or occupancy.”
- Alteration, filed Aug 17, 2018, estimated cost $15K, described as “Supported Scaffold installation as per plans submitted. No change in use, egress or occupancy.”

## Property taxes

- Assessment: $78,464,250
- 2026–27 tax: $370,128
- Market value (city estimate): $174,365,000
- Taxable value: $0
- Assessed land: $15,090,300
- Assessed improvements: $63,373,950

## Tax breaks

- Mitchell-Lama exemption, with no end date.

## Zoning

R7-2: floor area ratio 3.19 built, 3.44 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.