## Building permits

- Alteration, filed Nov 4, 2026, estimated cost $3K, described as “Modifications to the existing plumbing system on the (3rd Floor Suite 300 - Zymeworks) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Nov 3, 2026, estimated cost $10K, described as “Modifications to the existing HVAC system on the (3rd Floor Suite 300 - Zymeworks) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Oct 27, 2026, estimated cost $7K, described as “Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the (3rd Floor - Suite 300- Zymeworks ) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Oct 2, 2026, estimated cost $213K, described as “Fire escape emergency repairs as per drawings. There is no change to use, egress, or occupancy”
- Alteration, filed Aug 5, 2026, described as “Installation of temporary sidewalk shed as per plan. There is no change in use, egress, or occupancy.”
- Alteration, filed Jun 29, 2026, estimated cost $40K, described as “Modifications to the existing sprinkler system on the 8th Floor (Avoro Capital) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jun 29, 2026, estimated cost $140K, described as “Modifications to the existing HVAC system on the 8th Floor (Avoro Capital) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jun 29, 2026, estimated cost $30K, described as “Modifications to the existing plumbing system on the 8th Floor (Avoro Capital) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jun 26, 2026, estimated cost $500K, described as “Interior renovation with installation of new partitions, doors, ceilings and finishes on the 8th floor (Avoro Capital) as per plans. No change to use, egress or occupancy.”
- Alteration, filed May 1, 2026, described as “IRA to assist with Condition Assessment”
- Alteration, filed Aug 20, 2025, estimated cost $15K, described as “Modifications to the existing HVAC system on the 12th and 13th floors as per plans. No change to use, egress or occupancy.”
- Alteration, filed Aug 20, 2025, estimated cost $4K, described as “Modifications to the existing sprinkler system on the 13th floor as per plans. No change to use, egress or occupancy.”
- Alteration, filed Aug 20, 2025, estimated cost $40K, described as “Minor demolition with installation of new partitions, doors, ceilings and finishes on the 12th and 13th floors as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jul 21, 2025, estimated cost $12K, described as “Minor demolition with installation of new partitions, doors, ceilings and finishes on the 6th floor (Suite 600A & 600B) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jul 21, 2025, estimated cost $17K, described as “Modifications to the existing HVAC system on the 6th floor (Suite 600A & 600B) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jul 21, 2025, estimated cost $10K, described as “Modifications to the existing sprinkler system on the 6th floor (Suite 600A & 600B) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Aug 26, 2024, estimated cost $900, described as “Erect 3 illuminated interior window signs. Signs are accessory, non advertising for balenciaga”
- Alteration, filed Jul 31, 2024, estimated cost $9K, described as “Modifications to the existing HVAC system on the (7th Floor - Joe & The Juice Suite 703 - Office Renovation) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jul 31, 2024, estimated cost $6K, described as “Modifications to the existing plumbing system on the (7th Floor -Joe & The Juice Suite 703 - Office Renovation) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Jul 30, 2024, estimated cost $55K, described as “Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the (7th Floor - Joe & The Juice Suite 703 - Office Renovation) as per plans. No change to use, egress or occupancy.”
- Alteration, filed Apr 23, 2024, estimated cost $64K, described as “General construction modifications on the 5TH floor (suite 503) per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Apr 23, 2024, estimated cost $19K, described as “Plumbing modifications on the 5TH floor (suite 503) per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Apr 23, 2024, estimated cost $6K, described as “Mechanical systems modificatons on the 5TH floor (suite 503) per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Mar 14, 2024, estimated cost $9K, described as “General construction modifications and removal of non load-bearing partitions on the 7TH floor per plans. No change in use, egress, or occupancy.”
- Alteration, filed Feb 15, 2024, estimated cost $1K, described as “Installation of plywood enclosure as per plans. No change in egress, use, or occupancy.”

47 more, older permits are in this building’s full list on the map: https://umarelli.org/nyc/1004990007/104-greene-street.

## Property taxes

- Assessment: $28,290,150
- 2026–27 Tax: $2,815,102
- Market value (city estimate): $62,867,000
- Taxable value: $25,950,420
- Assessed land: $3,096,000
- Assessed improvements: $25,194,150

## Zoning

M1-5/R7X: floor area ratio 14.00 built, above the 5.00 base zoning allows, which bonuses, transfers or older rules can permit.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Landmarks

Part of SoHo-Cast Iron Historic District (Historic District). 50 Landmarks Preservation Commission permits are on file.

## Board and land use applications

- SoHo/NoHo (City Planning 2018M0375): Zoning map change, Zoning text change, Completed, decided Aug 25, 2022. SoHo/NoHo Neighborhood Plan seeks to strengthen SoHo and NoHo as mixed-use neighborhoods and promote equity. The proposal will expand housing opportunities for New Yorkers, reduce burdens for residents and businesses, and support continued…
- 110 Greene Street (New Application) (City Planning P2013M0334): Completed, decided Jun 3, 2014. Special Permit pursuant to ZR Section 74-781 to allow Use Group 6 retail on the first floor and cellar
- 110 GREENE ST (Application Withdrawn) (City Planning P2012M0027): Completed, decided Jan 31, 2013. Authorization permitting conversion to Joint Living-Work Quarters for Artists (JLWQA) and office/retail use. Certification for a waiver of the required rooftop recreation space.
- 110 GREENE STREET (City Planning P2007M0407): Completed. 07DCP012M: TO ALLOW A CHNGE OF USE TO LIVE-WORK UNITS ON FLRS 5-13 WITH AN ADDITION OF RETAIL IN THE BASEMENT AND SUB-BASEMENT
- GREENE ST (City Planning P1991M0001): Completed, decided Dec 24, 1991. SPECIAL PERMIT TO CONVERT 1ST FLOOR & CELLAR FROM COMMERCIAL\*USE TO RETAIL USE IN AN M1-5A DIST
- 104-110 GREENE STREET (City Planning P1991M0068): Completed, decided Feb 8, 1991. AUTHORIZATION (ZR42-14D, 5 (B) TO ALLOW A NON-PROFIT MUSEUM\*ON THE CELLAR FLOOR IN AN M1-5A DISTRICT
- 104-110 GREENE ST A/K/A 123-125 MERCER ST (City Planning P1983M0450): Completed, decided Dec 5, 1985. SPEC PERM TO CONVRT FLRS 9,10,12 & PENTHOUSE TO JOINT/LIVING\*WRK QRTRS FOR ARTISTS-M1-5A DIST (LT7)