25 West 4th Street, Manhattan
Commercial · built c. 1920 · Block 546, Lot 26.
Building permits
- Alteration, filed Feb 7, 2024, described as “Post Approval Amendment filed here in to add the option to use post-installed anchors for tieback. Installation and use of suspended scaffold for facade repair and inspection.”
- Alteration, filed Dec 22, 2023, estimated cost $10K, described as “Installation of temporary loading dock as per plans during general construction work. No change in use, egress or occupancy. Loading dock to comply with chapter 33 of NYC building code of 2024.”
- Alteration, filed Dec 4, 2023, estimated cost $5K, described as “Installation of temporary work platform as per plans during general construction work. No change in use, egress or occupancy. Work platform shall comply with chapter 33 of NYC building code.”
- Alteration, filed Aug 31, 2023, estimated cost $5K, described as “Installation of a temporary spyder crane as per plans in conjunction with general construction .no change in use, egress or occupancy. Spyder crane installed in accordance with 2022 NYC building code, chapter 33.”
- Alteration, filed Aug 30, 2023, estimated cost $10K, described as “Installation of a personnel/material construction hoist as per plans in conjunction with general construction. No change in use, egress or occupancy. Hoist installed in accordance with 2022 NYC building code, chapter 33”
- Alteration, filed Jul 27, 2023, estimated cost $10K, described as “Installation of temporary construction fence as per plans during general construction work. No change in use, egress or occupancy. Fence to comply with chapter 33 of NYC building code of 2022.”
- Alteration, filed Jul 11, 2023, estimated cost $10K, described as “Installation of temporary roof protection as per plans during general construction work. No change in use, egress or occupancy. Roof protection to comply with chapter 33 of NYC building code of 2014.”
- Alteration, filed Jun 1, 2023, estimated cost $10K, described as “Installation of a temporary overhead protection enclosure as per plans. No change in use, egress or occupancy. Overhead protection & enclosure installed in accordance with the 2022 NYC building code, chapter 33.”
- Alteration, filed May 31, 2023, estimated cost $5K, described as “Installation of a heavy duty sidewalk bridge as per plans in conjunction with general construction . No change in use, egress or occupancy. Sidewalk bridge to comply with 2022 NYC building code, chapter 33.”
- Alteration, filed Jan 4, 2023, estimated cost $1.5M, described as “All new plumbing systems for 2FL - 6FL and plumbing modificationssub-cellar to first floor as required. New 6" fire sprinkler service with backflow device. Sprinkler booster pump with dedicated fire service. A new sprinkler riser, temp loop”
- Alteration, filed Jan 4, 2023, estimated cost $5.3M, described as “Mechanical modifications. Removal, relocation and installation of AC units, Heating units, fan, duct, piping, pump,”
- Alteration, filed Nov 9, 2022, estimated cost $7.2M, described as “Interior building renovation/infrastructure upgrades, new elevator pit/shaft, floor/wall penetrations, facade repairs, window/storefront replacements. Modification to Egress stair B routing from 2nd floor to grade level Directive 2/75…”
- Alteration, filed May 4, 2022, estimated cost $1K, described as “Installation of temporary shoring as per plans. No change in use, egress or occupancy.”
Building history
- Alteration, filed Nov 15, 2016, permit issued - entire job/work, described as “Alterations to commercial space to create new admission center as per plans submitted herewith.”
New buildings, demolitions and major alterations filed in the city’s older system since 1989.
Property taxes
- Assessment
- $4,991,850
- Market value (city estimate)
- $11,093,000
- Taxable value
- $0
- Assessed land
- $783,000
- Assessed improvements
- $4,208,850
Tax breaks
- Nonprofit exemption (college or university), with no end date, about $541,516 a year below the full tax.
Zoning
R7-2: floor area ratio 5.73 built, above the 3.44 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- NYU CORE, MERCER ST., BLEECKER ST. (City Planning P2012M0059): Completed, decided Jul 31, 2012. 11DCP121M: NYU IS SEEKING A NUMBER OF DISCRETIONARY ACTONS IN CONNECTIO N W/ THE PROPOSED EXPANSION OF NYU FACILITIES AS ITS ACADEMI C CORE NEAR WASHINGTON SQUARE