Building permits
- Alteration, filed Oct 1, 2024, estimated cost $55K, described as “Modification of exist gas piping, replacement of exist gas riser cellar - 3rd floor, Cap & remove 8 gas meters on 4,5,6,7,8,8,9,10, Installation of new gas meter in cellar as per plans attached herewith. No change in use, egress and…”
- Alteration, filed Jul 18, 2022, estimated cost $75K, described as “Protection and Sequencing for the Creation of the new stair opening in existing concrete slab and Window opening in exterior masonry wall. No change in use, egress or occupancy.”
- Alteration, filed Jul 18, 2022, estimated cost $75K, described as “Creation of the new stair opening in existing concrete slab and design of a custom steel convenience stair.”
- Alteration, filed Jun 24, 2022, estimated cost $25K, described as “Modifications to existing plumbing systems. No change in use, egress or occupancy,”
- Alteration, filed Jun 23, 2022, estimated cost $350K, described as “Combination of apartment. Create opening in slab between levels and add a conveniencestair. Remove/relocate non structural partitions on both levels. No change in use, egress or occupancy.”
- Alteration, filed Jun 23, 2022, estimated cost $20K, described as “Modifications to existing sprinkler systems. No change in use, egress or occupancy.”
- Alteration, filed Jun 23, 2022, estimated cost $100K, described as “Modifications to existing mechanical systems. No change in use, egress or occupancy.”
- Alteration, filed Mar 25, 2021, estimated cost $427K, described as “Facade repairs as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jan 29, 2021, described as “Installation of temporary pipe scaffold as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jan 29, 2021, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Feb 27, 2020, estimated cost $5K, described as “Fresh air duct-work for ventilation at bathrooms and kitchen at existing apartment on floor 008. Mechanical work. There is to be no change of use, occupancy, or egress.”
- Alteration, filed Feb 27, 2020, estimated cost $28K, described as “Installation and modification of plumbing fixtures of existing apartment on floor 008. Plumbing work. There is to be no change of use, occupancy, or egress”
- Alteration, filed Jun 13, 2019, described as “Installation of sidewalk shed as per plans. No change in use, egress or occupancy.”
Building history
- Alteration, filed May 1, 2017, signed off Jan 13, 2020, units 10 to 11, described as “General construction in conjunction with change of occupancy at third floor (front) unit from commercial to r-2 residential apartment.”
- Alteration, filed Apr 22, 2013, signed off Dec 14, 2018, units 9 to 10
- Alteration, filed Oct 14, 2004, permit issued - entire job/work, described as “Conversion of a commercial art studio to residential apartment at 4th floor level. Architectural work only as per plans. All other work to be filed under separate application. Amended Certificate of Occupancy to be obtained.”
- Alteration, filed Nov 15, 2001, signed off May 28, 2004, described as “Change use of apartment 3R to residential ug 2 . Interior renovation of partitions no change to any other portion of the bldg.”
- Alteration, filed Jun 12, 2001, signed off Jul 2, 2004, described as “No work to be done under this applicatio n. Filinf to show apartment at th floor, all work previousy done under separate application. Alt #101990366”
- Alteration, filed Feb 18, 2000, plan exam - approved, described as “Install one(1) AC unit per plans, minor construction work Change use in unit 6R from Art Studio to Apartment/Art Studio. Obtain Amended Certificate of Occupancy #106773”
New buildings, demolitions and major alterations filed in the city’s older system since 1989.
Property taxes
- Assessment
- $7,025,125
- 2026–27 Tax
- $690,542
- Market value (city estimate)
- $15,611,386
- Taxable value
- $5,918,590
- Assessed land
- $965,699
- Assessed improvements
- $6,059,426
- Condo units with their own tax lots
- 14
Tax breaks
- Nonprofit exemption (charitable), with no end date, about $62,481 a year below the full tax.
Zoning
C6-3A: floor area ratio 7.47 built, 7.52 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, moderate risk: a 0.2% chance of flooding each year. FEMA’s preliminary map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 11 ft (NAVD88).
Recent sales
- Dec 8, 2022: $4,000,000, Unit GNDFL
- Jul 6, 2022: $2,060,000, Apt 3FL-R
- Sep 22, 2021: $1,700,000, Apt 8FL-F
- Apr 30, 2019: $2,300,000, Apt 8FL-R
- Feb 22, 2019: $2,625,000, Apt 7FL-F
- Jan 18, 2017: $1,750,000, Apt 3FL-F
- Dec 2, 2016: $5,100,000, Apt 2FL
Open-market sales since 2016, from the Department of Finance’s sales files.