521 West 25th Street, Manhattan
Commercial · built c. 1901 · Block 697, Lot 13.
Building permits
- Alteration, filed Aug 24, 2026, estimated cost $200K, described as “Lobby - removal and installation of interior partitons, flooring and ceilings. No change in use, egress or occupancy.”
- Alteration, filed Jun 17, 2026, estimated cost $78K, described as “Installation of temporary sprinkler loop on the 1ST to 4TH floor.”
- No Work, filed Mar 11, 2026
- Alteration, filed Nov 17, 2025, estimated cost $5K, described as “Temporary Installation to be used on a temporary event "Spotify Presents : Wicked". All the Installations are to be removed upon completion of the event.”
- Alteration, filed Aug 26, 2025, estimated cost $500K, described as “Accessory office - installation of mechanical ductwork and ac unit.”
- Alteration, filed Aug 26, 2025, estimated cost $40K, described as “Accessory office - installation of plumbing fixtures and related piping.”
- Alteration, filed Aug 26, 2025, estimated cost $700K, described as “Accessory office - removal and installation of interior partitons, flooring and ceilings. No change in use, egress or occupancy.”
- Alteration, filed Jul 31, 2025, estimated cost $504K, described as “Storage area - structural work. Details provided in the comments box below and on the drawings.”
- Alteration, filed Jul 31, 2025, estimated cost $58K, described as “Storage - foundation for new retaining walls in the loading/parking area on the 1ST floor in conjunction with slab replacement filed under separate application.”
- Alteration, filed Jul 30, 2025, estimated cost $2.5M, described as “Storage - removal and installation of sprinkler heads and related piping. Installation of additonal standpipe main piping, riser and hose racks off existing standpipe water service.”
- Alteration, filed Jul 29, 2025, estimated cost $60K, described as “Storage - installation of plumbing fixtures and related water/sanitary piping.”
- Alteration, filed Jul 29, 2025, estimated cost $870K, described as “Storage - installation of mechanical ductwork and ac units.”
- Alteration, filed Jul 16, 2025, estimated cost $5.7M, described as “Change use from factory to self-storage , accessory loading area, accessory retail office, and accessory offices. Related general construction.”
- Alteration, filed Sep 17, 2024, estimated cost $5K, described as “Temporary Installation to be used on a temporary event "Merrell". All the Installations are to be removed upon completion of the event.”
- Alteration, filed Jun 20, 2022, estimated cost $425K, described as “Foundation work taking place on the GRD floor as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed May 23, 2022, estimated cost $425K, described as “Structural modifications taking place on the GRD floor as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed May 17, 2022, estimated cost $30K, described as “Plumbing modifications taking place on the GRD floor as per plans filed herewith. No change in in use, egress or occupancy.”
- Alteration, filed May 17, 2022, estimated cost $85K, described as “Sprinkler modifications taking place on the GRD floor as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed May 17, 2022, estimated cost $275K, described as “General construction taking place in the GRD floor as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed May 17, 2022, estimated cost $75K, described as “Mechanical modifications taking place on the GRD floor as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Feb 22, 2022, estimated cost $30K, described as “Plumbing modifications on the 3rd and 4th floors as per plans filed herewith. No change is use, egress or occupancy.”
- Alteration, filed Feb 22, 2022, estimated cost $100K, described as “General construction taking place on the 3rd and 4th floors as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Feb 22, 2022, estimated cost $10K, described as “Mechanical modifications taking place on the 3rd and 4th floors as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Feb 22, 2022, estimated cost $10K, described as “Sprinkler modifications taking place on 3rd and 4th floors as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Sep 14, 2021, estimated cost $10K, described as “Plumbing modifications taking place on GRD floor as per drawings filed herewith. No change in use, egress or occupancy.”
9 more, older permits are in this building’s full list on the map.
Property taxes
- Assessment
- $14,413,500
- 2026–27 tax
- $1,516,850
- Market value (city estimate)
- $32,030,000
- Taxable value
- $13,982,760
- Assessed land
- $3,332,700
- Assessed improvements
- $11,080,800
Zoning
M1-5: floor area ratio 3.28 built, 5.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, moderate risk: a 0.2% chance of flooding each year. FEMA’s preliminary map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 11 ft (NAVD88).
Recent sales
- Jan 21, 2025: $49,500,000, sold with other lots
- May 23, 2019: $148,254,147, sold with other lots
Open-market sales since 2016, from the Department of Finance’s sales files.
Landmarks
Part of West Chelsea Historic District (Historic District). 39 Landmarks Preservation Commission permits are on file.
Board and land use applications
- 521-11 W25TH ST (City Planning P1980M0610): Completed, decided May 1, 1980. PURCHASE FOR MANUFACTURING USE