Building permits
- Alteration, filed Jul 7, 2026, described as “Industrial rope access for facade inspections.”
- No Work, filed Apr 20, 2026
- Alteration, filed Mar 18, 2026, estimated cost $84K, described as “Application is filed for interior demolition andrenovation in cellar that doesn't affect use, egress oroccupancy of the space, and therefore, no new or amendedcertificate of occupancy is required”
- Alteration, filed Jan 29, 2026, estimated cost $12K, described as “Modify existing Sprinkler head layout as part of renovation for tenant spaces at 11th floor of existing commercial space. No change to use, egress or occupancy.”
- Alteration, filed Jan 21, 2026, estimated cost $43K, described as “Interior renovation to create two separate tenant spaces at 11th floor of existing commercial space including installation of new pantry. No change to use, egress or occupancy.”
- Alteration, filed Jan 21, 2026, estimated cost $16K, described as “Install new piping, new plumbing fixtures and appliances as part of renovation for tenant spaces at 11th floor of existing commercial space including work at existing risers and shaft walls. No change to use, egress or occupancy.”
- Alteration, filed Jan 9, 2026, estimated cost $15K, described as “Modify exisitng Sprinkler head layout at 2nd and 3rd floors of existing commercial building. No change to use, egress or occupancy.”
- Alteration, filed Oct 24, 2025, estimated cost $38K, described as “Interior renovation of existing commercial space at 11th floor to include removal of existing wall partitions and installation of new 1-hour fire-rated wall partition around the existing communicating stair. No change to use, egress or…”
- Alteration, filed Oct 24, 2025, estimated cost $8K, described as “Install one (1) new sprinkler head and relocate a total of three (3) sprinkler heads to facilitate Office Renovation at 9th Floor South. No change to use, egress or occupancy.”
- Alteration, filed Oct 24, 2025, estimated cost $31K, described as “Installation of new full & partial-height gypsum wall board partitions, pantry millwork & appliances, relocated glass walls & relocation of existing light fixture to facilitate Office Renovation at 9th Floor South. No change to use, egress…”
- Alteration, filed Oct 22, 2025, estimated cost $8K, described as “Install new pantry sink, pantry dishwasher, hot water heater, refrigerator, coffee machine and associated plumbing piping and connections to facilitate Office Renovation at 9th Floor South. No change to use, egress or occupancy.”
- Alteration, filed Jun 24, 2025, estimated cost $400K, described as “Interior Renovation at floors 6-8 of existing commercial office space in an existing building. No change to use, egress or occupancy.”
- Alteration, filed Jun 24, 2025, estimated cost $9K, described as “Modify existing air distribution for floors 6 through 8 in an existing commercial space. No change in use, egress or occupancy.”
- Alteration, filed Jun 24, 2025, estimated cost $10K, described as “Modification of existing sprinkler head layout for floors 6 through 8 in a commercial space. No change in use, egress or occupancy.”
- Alteration, filed Jun 24, 2025, estimated cost $15K, described as “Plumbing related work for interior commercial space at floors 6 to 8. No change in use, egress or occupancy”
- Alteration, filed Apr 11, 2024, estimated cost $33K, described as “General Construction related to interior renovation at 5th and 6th floors of an existing commercial building. No changes to use, egress, or occupancy.”
- Alteration, filed Jun 29, 2023, estimated cost $50K, described as “Minor plumbing alteration in association with renovation of existing commercial space on the 9th Floor. No Change to use, egress or occupancy”
- Alteration, filed Jun 29, 2023, estimated cost $75K, described as “Modification of existing Mechanical Systems in association with renovation of existing commercial space on the 9th Floor. No change to use egress or occupancy.”
- Alteration, filed Jun 28, 2023, estimated cost $250K, described as “Interior renovation of 9th Floor existing commercial space including but not limited to partition work, finishes & millwork. No change to use, egress or occupancy.”
- Alteration, filed Jun 28, 2023, estimated cost $30K, described as “Minor modification to existing sprinkler system including relocation and installation of new sprinkler heads in association with renovation of existing commercial space on the 9th Floor. No Change to use, egress or occupancy”
- Alteration, filed Nov 8, 2021, estimated cost $60K, described as “Filing herewith for removal of non load bearing interior partitions as indicated and new interior partition work. No change to use, egress or occupancy.”
- Alteration, filed Aug 9, 2018, described as “Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Mar 22, 2018, described as “Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
Property taxes
- Assessment
- $13,469,850
- 2026–27 tax
- $1,442,606
- Market value (city estimate)
- $29,933,000
- Taxable value
- $13,298,360
- Assessed land
- $976,500
- Assessed improvements
- $12,493,350
Zoning
C6-2A: floor area ratio 13.78 built, above the 6.02 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- Variance or special permit (Board of Standards and Appeals 237-12-BZ): Variance or special permit, Granted, filed Aug 1, 2012, decided Dec 4, 2012. Special Permit (§73-36) to allow a physical culture establishment (Crunch). C6-4A zoning district.
In the news
The Corcoran Group Relocates To Full-Floor Of 220 West 19th Street In Chelsea, Manhattan, New York YIMBY, Apr 20, 2024.