255 West 34th Street, Manhattan
Hotel · built 2021 · Block 784, Lot 12.
Building permits
- Alteration, filed Oct 13, 2026, estimated cost $350, described as “Install exterior indirectly illuminated double faced banner sign on wall (bar leo)”
- Alteration, filed Oct 13, 2026, estimated cost $3K, described as “Install exterior illuminated wall sign (canopy by hilton)”
- Alteration, filed Oct 13, 2026, estimated cost $350, described as “Install exterior indirectly illuminated double faced banner sign on wall (bar leo)”
- Alteration, filed Oct 13, 2026, estimated cost $350, described as “Install exterior indirectly illuminated double faced banner sign on wall (canopy by hilton)”
- Alteration, filed Oct 13, 2026, estimated cost $450, described as “Install exterior non-illuminated wall sign (solenne)”
- Alteration, filed Oct 13, 2026, estimated cost $350, described as “Install exterior indirectly illuminated double faced banner sign on wall (canopy by hilton)”
- Alteration, filed Oct 13, 2026, estimated cost $350, described as “Install exterior indirectly illuminated double faced banner sign on wall (canopy by hilton)”
- Alteration, filed Oct 13, 2026, estimated cost $350, described as “Install exterior indirectly illuminated double faced banner sign on wall (canopy by hilton)”
- Alteration, filed Oct 5, 2026, described as “Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed May 26, 2026, described as “Installation of suspended scaffold for facade inspection /repair.”
- No Work, filed Apr 22, 2026
- No Work, filed Apr 9, 2026
- No Work, filed Apr 9, 2026
- No Work, filed Apr 9, 2026
- Alteration, filed Jan 6, 2026, estimated cost $4K, described as “Installation of temporary roof protection as per plans. No change in use, egress or occupancy.”
- Alteration, filed Nov 21, 2025, estimated cost $1K, described as “Installation and use of temporary loading platforms as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Oct 9, 2025, described as “Installation of temporary suspended scaffold equipment.”
- Alteration, filed Aug 8, 2025, estimated cost $26K, described as “Installation of pipe scaffolding as per plans. Pipe scaffold shall comply with chapter #33 of the 2022 code. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 8, 2025, described as “Installation of suspended scaffold for facade inspection /repair.”
- Alteration, filed Jul 30, 2025, estimated cost $49K, described as “Application filed for temporary shoring and support of excavation only in order to install Con Edison Transformer Vaults under separate application. Major Projects # MPP 320”
- Alteration, filed May 14, 2025, described as “Installation of suspended scaffold for facade inspection/repair.”
- Alteration, filed Apr 25, 2025, estimated cost $1K, described as “Installation and use of temporary mini crane climber as per plan filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Mar 21, 2025, described as “Temporary suspended scaffold as per drawings during NB const, filed sep. Suspended scaffold shall comply with ch 33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Mar 19, 2025, estimated cost $3K, described as “Herewith for the installation of a fuel storage Tank and related piping, in conjunction with the installation of an emergency generator, as part of NB Application 122745100.”
- Alteration, filed Mar 13, 2025, estimated cost $5K, described as “Installation and use of temporary contractor's shed/field office as per plans filed herewith.”
12 more, older permits are in this building’s full list on the map.
Property taxes
- Assessment
- $14,726,700
- 2026–27 tax
- $1,591,343
- Market value (city estimate)
- $32,726,000
- Taxable value
- $14,669,460
- Assessed land
- $3,689,550
- Assessed improvements
- $11,037,150
Zoning
C6-4M: floor area ratio 19.98 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- 484 8th Avenue - Subway Stair Relocation (City Planning 2026M0519): Certification, Completed, filed Aug 12, 2026, decided Sep 16, 2026. A zoning certification pursuant to ZR Section 37-43 to modify the requirements of ZR Section 37-41 for the relocation of the existing A/C/E subway stair to be located in a proposed as-of-right mixed-use building on 484 8th Avenue…
In the news
255 West 34th Street’s Exterior Progresses in Midtown, Manhattan, New York YIMBY, Feb 20, 2026.