# 111 West 19th Street, Manhattan

Commercial · built c. 1901 · Block 795, Lot 28.

Some of the city’s records for this lot were still loading when this page was made; it refreshes within minutes.

On Umarelli: https://umarelli.org/nyc/1007950028/111-west-19-street

More construction in Chelsea: https://umarelli.org/nyc/manhattan/chelsea.md

Every lot on block 795: https://umarelli.org/nyc/manhattan/795.md

## Building permits

- Alteration, filed Apr 15, 2026, described as “Application for the installation and use of suspended scaffold”
- Alteration, filed Dec 22, 2025, estimated cost $58K, described as “Tenant improvement to existing office space at this location. No change in use, egress, or occupancy under this application.”
- Alteration, filed Nov 20, 2025, estimated cost $1.6M, described as “General construction to 6TH and 7TH floor for "ripple" as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Nov 19, 2024, estimated cost $200K, described as “Mechanical work for installing a new water-cooled packaged A/C unit AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.”
- Alteration, filed May 16, 2024, described as “Application for the installation and use of suspended scaffold”
- Alteration, filed Feb 20, 2024, estimated cost $100K, described as “General construction as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Feb 15, 2024, estimated cost $3.0M, described as “General construction to 6TH floor for "ripple" as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Dec 29, 2023, estimated cost $500K, described as “General construction to 6th floor as per plans filed herewith. no change to use, egress or occupancy.”
- Alteration, filed May 11, 2022, estimated cost $1K, described as “Proposed installation of temporary pipe scaffold as per plans. Work shall comply with chapter #33 of the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed May 11, 2022, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of the NYC building code. Live load 300PSF.”
- Alteration, filed Dec 3, 2021, described as “Sidewalk shed installed as per plans. There are no changes in use, egress or occupancy.”
- Alteration, filed Dec 3, 2021, described as “Installation of supported scaffold as per plans/ There are no changes in use, egress or occupancy.”
- Alteration, filed Nov 4, 2021, estimated cost $15K, described as “Sprinkler work for "outbrain" as per plans filed herewith. no change to use, egress or occupancy.”
- Alteration, filed Nov 4, 2021, estimated cost $20K, described as “Mechanical work for "outbrain" as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Nov 2, 2021, estimated cost $310K, described as “Interior renovation to 3RD floor for "outbrain" as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed May 7, 2020, estimated cost $250K, described as “Mechanical work as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed May 11, 2018, described as “Installation of pipe scaffold as per plans. No change in use, egress or occupancy.”
- Alteration, filed Apr 25, 2018, described as “Installation of heavy duty sidewalk shed as per plans. No change in use, egress or occupancy.”

## Building history

- Alteration, filed Feb 28, 2012, plan exam - disapproved, described as “Change of occupancy &amp; use of entire building-cellar through 8TH fl. No change in height &amp; fl area.”
- Alteration, filed Nov 19, 2007, plan exam - disapproved, described as “Change use of building to retail on cellar, 1ST and mezz. Floors. Adult trade school on 2ND, 4TH, 5TH, and 6TH floors. Factory on 7TH floor, offices on 3RD. Floor and warehouse on 8TH floor. No work to be done under this application . All…”
- Alteration, filed Oct 28, 2004, permit issued - entire job/work, described as “Install new demising partitions, convert the existing storage area to bridal / tailoring shop, use group 10 as shown on drawings. Filed in conjunction with Dir. 14 #103954491.”
- Alteration, filed Jun 14, 1999, plan exam - disapproved, described as “Filing to change the use and occupant load on the 2nd, 4th, 5th and 6th floors. All work to be filed under separate application.”

New buildings, demolitions and major alterations filed in the city’s older system since 1989.

## Property taxes

- Assessment: $23,598,450
- 2026–27 Tax: $2,508,830
- Market value (city estimate): $52,441,000
- Taxable value: $23,127,120
- Assessed land: $2,493,000
- Assessed improvements: $21,105,450

## Zoning

C6-3A: floor area ratio 9.00 built, above the 7.52 base zoning allows, which bonuses, transfers or older rules can permit.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology