## Building permits

- Alteration, filed Oct 1, 2026, estimated cost $5K, described as “Temporary pipe scaffold as per drawings. Scaffold shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Aug 18, 2026, estimated cost $226K, described as “General construction modifications taking place on the 7TH floor as per drawings filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Jul 30, 2026, estimated cost $5K, described as “Mechanical filing to obtain Equipment Use Permits (COC) for existing AC units on the roof as indicated on drawings to comply with FDNY summons 014165612M & 014259875L”
- Alteration, filed Jan 30, 2025, estimated cost $257K, described as “Partial removal of non-bearing partitions, finishes, and doors. Removal of existing electrical work. No change to use, egress or occupancy.”
- Alteration, filed Nov 21, 2024, estimated cost $12K, described as “Structural work to infil slab opening on the 2nd floor as indicated on drawings.”
- Alteration, filed Oct 9, 2024, estimated cost $15K, described as “Temporary pipe scaffold as per drawings. Scaffold shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Feb 27, 2024, estimated cost $3K, described as “Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Feb 20, 2024, described as “Installation of outriggers for facade repair and inspection”
- Alteration, filed Oct 19, 2023, estimated cost $225K, described as “Repairs to exterior facades. No change to egress, use or occupancy.”
- Alteration, filed Oct 21, 2020, estimated cost $36K, described as “Sprinkler changes on the 6th floor as indicated on drawings. No change in use, egress or occupancy. This work will supercede work filed under application # 102820048.”
- Alteration, filed Oct 23, 2019, estimated cost $125K, described as “Installation of vrf HVAC system on the 9TH floor & roof. No change in use egress or occupancy.”

## Building history

- Alteration, filed May 16, 1990, permit issued - partial job, described as “Convert existing commercial space into a billiard parlor at cellar a irst floor and golf facility at second f loor including new plumbing and part n work.”

New buildings, demolitions and major alterations filed in the city’s older system since 1989.

## Property taxes

- Assessment: $11,635,650
- 2026–27 Tax: $1,226,790
- Market value (city estimate): $25,857,000
- Taxable value: $11,297,450
- Assessed land: $1,440,000
- Assessed improvements: $10,195,650

## Zoning

M1-8A/R11: floor area ratio 11.46 built, 12.00 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Board and land use applications

- Midtown South Mixed-Use Plan (MSMX) (City Planning 2024M0142): Zoning Map Change, Zoning Text Change, Completed, filed Jan 16, 2025, decided Aug 14, 2025. The Department of City Planning is seeking a Zoning Map amendment from M1-6 and M1-6D to M1-9A/R12, M1-8A/R12, and M1-8A/R11 and a Zoning Text amendment to facilitate the development of housing and support critical economic activity across…