Apartment building · 41 units · built 2023 · Block 830, Lot 44.
Building permits
- Alteration, filed Sep 17, 2026, estimated cost $1K, described as “Installation of temporary protection as per plans. No change in use, egress or occupancy shall comply with CHAPTER#33 of 2022 the ny building code.”
- Alteration, filed Sep 17, 2026, estimated cost $1K, described as “Installation of temporary platform as per plans. No change in use, egress or occupancy shall comply with CHAPTER#33 of 2022 the ny building code.”
- Alteration, filed Sep 2, 2026, estimated cost $5K, described as “Installation and use of temporary Building Maintenance Unit (BMU) construction equipment as per plans filed herewith.”
- Alteration, filed Jul 22, 2026, estimated cost $5K, described as “This application is filed for temporary use permit for a model apartment pursuant to section ac 28-111 and building bulletin 2010-002.”
- Alteration, filed Dec 8, 2025, described as “Installation of temporary suspended scaffolds per plan submitted. Work shall comply with 2022 building code chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Sep 3, 2025, described as “Installation of ADT suspended scaffold system”
- Alteration, filed Jul 20, 2025, estimated cost $1K, described as “Installation of temporary platform as per plans. No change in use, egress or occupancy shall comply with CHAPTER#33 of 2022 the ny building code.”
- Alteration, filed May 22, 2025, estimated cost $1K, described as “Installation of temporary working platform as per plan. No change in use, egress or occupancy”
- Alteration, filed Apr 11, 2024, estimated cost $1K, described as “Proposed installation of temporary pipe scaffold as per plans. Work shall comply with chapter #33 of 2022 the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Mar 13, 2024, estimated cost $1K, described as “Installation of horizontal netting as per plans. No change in use, occupancy, or egress under this application. Horizontal netting shall comply with chapter #33 of 2022 the NYC building code.”
- Alteration, filed Feb 21, 2024, estimated cost $10K, described as “Beams will be used to facilitate installation of facade panels of new building under construction. No changes to use or egress. Filed in relation to NB 122874906”
- Alteration, filed Nov 22, 2023, estimated cost $1K, described as “Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use or occupancy.”
- Alteration, filed May 10, 2023, estimated cost $20K, described as “Installation of a scaffold is to be supported by the working platform at each level and braced to the wall from level 13 to level 56. This application is filed in conjunction with applications # M00811904 & # 122874906”
- Alteration, filed Mar 2, 2023, estimated cost $84K, described as “Installation of temporary alternate protection as per plans filed herewith. This application is filed in conjunction with NB 122874906”
- Alteration, filed Feb 28, 2023, estimated cost $10K, described as “Exterior supported working platform used on floors 8, 15, 20, 26, 31, 27, 41, 44, 48, and 53 to make tower crane tie connections. No changes to the use or egress. Filed in relation to NB 122874906”
- Alteration, filed Jan 3, 2023, estimated cost $10K, described as “Exterior supported working and loading platform to be used on the typical floors to load and unload the materials. No changes to the use or to the egress. This application is filed in conjunction with NB 122874906”
- Alteration, filed Dec 2, 2022, estimated cost $10K, described as “Exterior supported working and loading platform to be used at the typical floors to load and unload the materials. No changes to the use or to the egress.”
- Alteration, filed Nov 4, 2022, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of the NYC building code. Live load 300PSF.”
- Alteration, filed Nov 4, 2022, estimated cost $1K, described as “Installation of temporary construction fence as per plans. No change in use, occupancy or egress.”
- Alteration, filed Nov 4, 2022, estimated cost $1K, described as “Installation of temporary roof protection as per plans. No change in use, egress or occupancy shall comply with CHAPTER#33 of 2014 the ny building code.”
- Alteration, filed Oct 10, 2022, estimated cost $1K, described as “Installation and use of temporary concrete placing boom as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Aug 2, 2022, estimated cost $10K, described as “Installation of temporary personnel/material hoist complex as per plans in conjunction with NB construction. No change in use, egress or occupancy. Hoist to comply with chapter 33 of NYC building code of 2014.”
- Alteration, filed Jul 15, 2022, estimated cost $1K, described as “Installation and use of concrete placing boom as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Jul 5, 2022, estimated cost $2K, described as “Install combined sprinkler/standpipe system as per plans filed herewith. Filed in conjunction with NB# 122874906”
- Alteration, filed Jun 23, 2022, estimated cost $1K, described as “Plumbing work per plans filed herewith.”
2 more, older permits are in this building’s full list on the map.
Property taxes
- Assessment
- $14,130,000
- 2026–27 tax
- $1,750,410
- Market value (city estimate)
- $31,400,000
- Taxable value
- $14,071,950
- Assessed land
- $2,220,300
- Assessed improvements
- $11,909,700
Zoning
C5-2: floor area ratio 38.15 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- 262 Fifth Avenue (City Planning 2022M0352): Special permit, Completed, filed Oct 14, 2022, decided Aug 30, 2023. A special permit pursuant to ZR Section 13-451 to facilitate a 23-space garage in a new 26-unit predominantly residential building, is being sought by Five Points JV L.P. at 262 5th Avenue in the NoMad neighborhood, Community District 5,…
- Flatiron BID Expansion (City Planning 2021M0260): Business improvement district, Completed, filed Nov 30, 2020, decided May 19, 2021. An application from the Small Business Services (SBS) on behalf of the Flatiron Business Improvement District (BID) to modify the existing plan and expand the BID in Community Districts 4 and 5 of Manhattan.