# 106 West 56th Street, Manhattan

Commercial · built 2018 · Block 1008, Lot 37.

On Umarelli: https://umarelli.org/nyc/1010080037/106-west-56-street

More construction in Midtown West: https://umarelli.org/nyc/manhattan/midtown-west.md

## Building permits

- Alteration, filed Jul 31, 2026, estimated cost $51K, described as “Application filed for interior renovation of non-load bearing partitions, ceilings, and finishes on the 4TH floor as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Jun 16, 2025, estimated cost $700K, described as “It is proposed to renovate 2FL of existing building for new tenant build-out as shown on plans. No change of use, egress or occupancy. Application filed in conjunction with subsequent application M01231906-S1 (ms) & M01231906-S2 (pl/sp)”
- Alteration, filed Apr 24, 2025, estimated cost $650K, described as “It is proposed to renovate 7FL of existing building for a build-out as shown on plans. No change of use, egress of occupancy. Application filed in conjunction w/ M01195452-S1 (ms) and M01195452-S2 (pl/sp)”
- Alteration, filed Mar 13, 2025, estimated cost $650K, described as “It is proposed to renovate 20FL (marketing 21) of existing b uilding for a build-out as shown on plans. No change of use, egress of occupancy. Application filed in conjunction w/ M01182059-S12 (ms) and M01182059-S2 (pl/sp)”
- Alteration, filed Jan 13, 2025, estimated cost $650K, described as “It is proposed to renovate the 22FL (23FL marketing) of existing building for a built-out as shown on plans. Application filed in conjunction with S1 (ms), S2(pl/sp).”
- Alteration, filed May 16, 2024, estimated cost $700K, described as “It is proposed to renovate 12FL of existing building for new tenant build-out as shown on plans. No change of use, egress or occupancy.”
- Alteration, filed Apr 2, 2024, estimated cost $133K, described as “Modification to mechanical system as per plans. No change in usse, egress or occupancy.”
- Alteration, filed Mar 29, 2024, estimated cost $51K, described as “Modification to plumbing/sprinkler as per plans. No change in usse, egress or occupancy.”
- Alteration, filed Mar 28, 2024, estimated cost $756K, described as “Installation of non-load bearing partitionas as per plans. No change in use, egress or occupancy.”
- Alteration, filed Feb 28, 2024, estimated cost $550K, described as “It is proposed to renovate 14FL for new tenant build-out as shown on plans. No Change of Use, Egress or occupancy. Application filed in conjunction with M00986083-S1 (MS), M00986083-S2 (PL), M00986083-S3 (SP)”
- Alteration, filed Nov 27, 2023, estimated cost $90K, described as “Filing mechanical system as per plans. No change in use, egress or occupancy.”
- Alteration, filed Nov 26, 2023, estimated cost $70K, described as “Plumbing/sprinkler system as per plans. No change inuse, egress or occupancy.”
- Alteration, filed Nov 22, 2023, estimated cost $1.2M, described as “Installation of non load bearingpartitions as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Feb 14, 2023, estimated cost $90K, described as “Filing mechanical system as per plans. No change in use, egress or occupancy.”
- Alteration, filed Feb 14, 2023, estimated cost $70K, described as “Plumbing/sprinkler system as per plans. No change inuse, egress or occupancy.”
- Alteration, filed Feb 10, 2023, estimated cost $1.2M, described as “Installation of non load bearingpartitions as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Sep 14, 2022, estimated cost $593K, described as “Installation of non load bearingpartitions as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Sep 12, 2022, estimated cost $45K, described as “Filing mechanical system as per plans. No change in use, egress or occupancy.”
- Alteration, filed Sep 12, 2022, estimated cost $35K, described as “Plumbing/sprinkler system as per plans. No change inuse, egress or occupancy.”
- Alteration, filed Apr 20, 2022, estimated cost $3.1M, described as “Installation of non load bearingpartitions as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Apr 19, 2022, estimated cost $236K, described as “Modification to mechanical system as per plans. No change in usse, egress or occupancy.”
- Alteration, filed Apr 19, 2022, estimated cost $182K, described as “Modification to plumbing and sprinkler plans. Removing the 20TH floor from the plans”
- Alteration, filed Mar 18, 2022, estimated cost $15K, described as “Install bracket supports for chimney extension on neighboring building.”
- Alteration, filed Aug 11, 2021, estimated cost $593K, described as “Installation of non load bearingpartitions as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Aug 11, 2021, estimated cost $1.8M, described as “Installation of non load bearingpartitions as per plans filed herewith. No change in use, egress or occupancy.”

13 more, older permits are in this building’s full list on the map: https://umarelli.org/nyc/1010080037/106-west-56-street.

## Property taxes

- Assessment: $18,338,400
- 2026–27 tax: $1,857,532
- Market value (city estimate): $40,752,000
- Taxable value: $17,123,270
- Assessed land: $3,060,000
- Assessed improvements: $15,278,400

## Zoning

C6-6: floor area ratio 17.44 built, above the 15.00 base zoning allows, which bonuses, transfers or older rules can permit.

## Recent sales

- Feb 12, 2016: $48,694,000

Open-market sales since 2016, from the Department of Finance’s sales files.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## In the news

[The Six Completes Construction at 106 West 56th Street in Midtown, Manhattan](https://newyorkyimby.com/2021/08/the-six-completes-construction-at-106-west-56th-street-in-midtown-manhattan.html), New York YIMBY, Aug 31, 2021.