230 West 49th Street, Manhattan
Commercial · built c. 1925 · Block 1020, Lot 53.
Building permits
- Alteration, filed Dec 31, 2024, estimated cost $1K, described as “Proposed installation of temporary light duty pipe scaffold as per plans. Work shall comply with chapter #33 of 2022 the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Oct 21, 2024, estimated cost $475K, described as “Mechanical work at hte eugene o'neill theater incl. (2) two new packaged rooftop air conditioning units along with new associated ductwork connections into existing air outlet distribution. No change of use, egress or occupancy.”
- Alteration, filed Aug 21, 2024, estimated cost $50K, described as “Facade repairs project. No change in use, egress or occupancy.”
- Alteration, filed Aug 21, 2024, estimated cost $800K, described as “Roofing System Replacement. No change in use, egress or occupancy.”
- Alteration, filed Jun 26, 2024, estimated cost $5K, described as “Installation of 40' new sidewalk shed as indicated on plans. There will be no change in the use, egress, or occupancy under this application”
- Alteration, filed Apr 12, 2023, estimated cost $400K, described as “Stone crack repair as shown on the plans filed herewith. no change to use, egress or occupancy”
- Alteration, filed Apr 5, 2023, estimated cost $1K, described as “Proposed installation of temporary pipe scaffold as per plans. Work shall comply with chapter #33 of 2022 the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Oct 11, 2022, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of the NYC building code. Live load 300PSF.”
- Alteration, filed Nov 3, 2021, estimated cost $1K, described as “No work application showing ADA viewing positions in the theatre as shown on plans filed herewith. No change to use, egress, or occupancy”
Property taxes
- Assessment
- $2,473,650
- 2026–27 tax
- $255,200
- Market value (city estimate)
- $5,497,000
- Taxable value
- $2,352,510
- Assessed land
- $1,507,500
- Assessed improvements
- $966,150
Zoning
C6-5: floor area ratio 4.00 built, 10.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Landmarks
Part of Forrest Theater, later the Coronet Theater, now the Eugene O'Neill Theater (Interior Landmark). 13 Landmarks Preservation Commission permits are on file.
Board and land use applications
- RITZ PLAZA (City Planning P1996M0191): Completed, decided Dec 23, 1998. 96DCP024M: AUTHORIZATION TO CLOSE URBAN PLAZA IN SPECIAL MIDTOWN DISTRI CT DURING NIGHTTIME HOURS, PURSUANT TO ZONING RESOLUTION 81- 231(S)
- EUGENE O'NEIL THEATRE, 1ST FL INTER (City Planning P1988M0417): Completed, decided Mar 10, 1988. LANDMARK-CITY COLLEGE OF NY, REMSEN CEMETERY,TROTTING*COURSE LA; Additional LPC #(s): 386