888 7th Avenue, Manhattan
Commercial · built 1970 · Block 1028, Lot 29.
Building permits
- Alteration, filed Nov 11, 2026, described as “Suspended Scaffold for Facade Restoration as Shown on Plans”
- Alteration, filed Oct 2, 2026, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Sep 9, 2026, estimated cost $180K, described as “Interior reno of existing it room. Work includes, but not limited to, demo/installation of non-load bearing partitions, fixtures and finishes on 30TH fl as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jun 30, 2026, estimated cost $1.6M, described as “JS Capital / One Madison Prebuild - Construction work on the 39th floor as indicated on drawings.”
- Alteration, filed Jun 24, 2026, estimated cost $59K, described as “JS Capital / One Madison Prebuild - Sprinkler work on the 39th floor as indicated on drawings.”
- Alteration, filed Jun 24, 2026, estimated cost $80K, described as “JS Capital / One Madison Prebuild - Plumbing work on the 39th floor as indicted on drawings.”
- Alteration, filed Jun 24, 2026, estimated cost $195K, described as “JS Capital / One Madison Prebuild - Mechanical work on the 39th floor as indicated on drawings.”
- Alteration, filed Jun 24, 2026, estimated cost $38K, described as “JS Capital / One Madison Prebuild - Structural work on the 39th & 40th floors to remove convenient stair and infill slab as indicated on drawings.”
- Alteration, filed Dec 17, 2025, estimated cost $350K, described as “General construction on the 17TH and 18TH floor as plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Dec 15, 2025, estimated cost $30K, described as “Plumbing work on the 17TH and 18TH floor as plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Dec 15, 2025, estimated cost $7K, described as “Sprinkler work on the 17TH and 18TH floors as plans filed herewith. No change in use, egress, or occupancy”
- Alteration, filed Dec 15, 2025, estimated cost $20K, described as “Mechanical work on the 17th and 18th floor as plans filed herewith. No change in use,egress, or occupancy.”
- Alteration, filed Sep 22, 2025, estimated cost $21K, described as “Structural work on the 21st floor (TI-Turnkey - Grace & Mercy) as indicated on drawings.”
- Alteration, filed Sep 16, 2025, estimated cost $75K, described as “Interior renovations as per plans filed herewith. No change in use, occupancy or egress.”
- Alteration, filed Aug 18, 2025, estimated cost $1.7M, described as “Structural work on sub-cellar 2, sub-cellar 1 and cellar levels (LL126 Parking Garage Repairs) as indicated on drawings.”
- Alteration, filed Jul 22, 2025, estimated cost $105K, described as “TI Turnkey - Grace & Mercy - Mechanical work on the 21st floor as indicated on drawings.”
- Alteration, filed Jul 22, 2025, estimated cost $10K, described as “TI Turnkey - Grace & Mercy - Sprinkler work on the 21st floor as indicated on drawings.”
- Alteration, filed Jul 16, 2025, estimated cost $199K, described as “TI Turnkey - Grace & Mercy - Construction work on the 21st floor as indicated on drawings.”
- Alteration, filed Jul 29, 2024, estimated cost $51K, described as “Cynosure - Mechanical work on the 23rd floor as indicated on drawings.”
- Alteration, filed Jul 29, 2024, estimated cost $403K, described as “Cynosure - Construction work on 23rd floor as indicated on drawings.”
- Alteration, filed Jul 24, 2024, estimated cost $10K, described as “Cynosure - Plumbing work on the 23rd floor as indicated on drawings.”
- Alteration, filed Jul 24, 2024, estimated cost $17K, described as “Cynosure - Sprinkler work on the 23rd floor as indicated on drawings.”
- Alteration, filed Mar 11, 2024, described as “Leak at north facade”
- Alteration, filed Mar 5, 2024, estimated cost $259K, described as “North facade work on the 11th, 12th, 13th & 14th floors to repair leak as indicated on drawings.”
- Alteration, filed Sep 28, 2023, estimated cost $5K, described as “Sixth Street - Sprinkler work on the part of the 41st & 42nd floors as indicated on drawings.”
116 more, older permits are in this building’s full list on the map.
Property taxes
- Assessment
- $187,186,500
- 2026–27 tax
- $19,083,200
- Market value (city estimate)
- $415,970,000
- Taxable value
- $175,914,450
- Assessed land
- $27,000,000
- Assessed improvements
- $160,186,500
Zoning
C6-6 (part of the lot is C5-3): floor area ratio 26.72 built, above the 15.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.