## Building permits

- Alteration, filed May 6, 2026, estimated cost $296K, described as “Propose to file to change the use group and occupancy load of the roof. No change in building height, size or bulk.”
- Alteration, filed Oct 3, 2025, estimated cost $157K, described as “Propose installation of (1) 16 ton heat pump with (3) 4.5 ton air -handling units, (1) 6 ton unit with (2) 3 ton AC units and (1) ERV. No change to use, egress or occupancy.”
- Alteration, filed Aug 18, 2025, estimated cost $740K, described as “Propose demolition of existing AC units including ductwork demolition and installation of new as per drawings. No change in use, egress or occupancy.”
- Alteration, filed Aug 18, 2025, estimated cost $246K, described as “Propose plumbing and sprinkler work as per drawings. No change in use, egress or occupancy.”
- Alteration, filed Aug 5, 2025, estimated cost $1.3M, described as “Propose interior renovations. No change in use, egress or occupancy.”
- Alteration, filed Jun 2, 2025, estimated cost $17K, described as “Propose installation of new plumbing fixtures and sprinkler heads. No change in use, egress or occupancy.”
- Alteration, filed Jun 2, 2025, estimated cost $101K, described as “Propose interior renovations. No change in use, egress or occupancy.”
- Alteration, filed Jun 2, 2025, estimated cost $68K, described as “Propose installation of split system HVAC unit. No change in use, egress or occupancy.”
- Alteration, filed Apr 25, 2025, estimated cost $34K, described as “Propose installation of new plumbing fixtures, sprinkler heads and associated branch piping. No change to use, egress or occupancy.”
- Alteration, filed Apr 23, 2025, estimated cost $56K, described as “Propose interior renovation at 1st floor of existing commercial building with partition work and finish work as per plan. No change in use, egress, or occupancy.”
- Alteration, filed Apr 10, 2025, estimated cost $275K, described as “Propose to perform tenant space interior partitions, new lighting on partial 2nd flr. No change in use, egress or occupancy.”
- Alteration, filed Apr 8, 2025, estimated cost $10K, described as “Danna's - filing herewith for the interior removal for the existing space. There will be no change in egress, occupancy or use.”
- Alteration, filed Feb 12, 2025, estimated cost $62K, described as “Propose to file for construction of staircase between 12th and 14th floor. No change in use, egress or occupancy.”
- Alteration, filed Jan 6, 2025, estimated cost $120K, described as “Installation of interior convenience stair. No change to use, egress or occupancy.”
- Alteration, filed Jan 3, 2024, estimated cost $33K, described as “Install sidewalk ramps to tenant entrances. No change in use, egress or occupancy.”
- Alteration, filed Sep 1, 2022, estimated cost $20K, described as “Propose to perform mechanical work. No change in use, egress or occupancy.”
- Alteration, filed Jun 15, 2022, estimated cost $73K, described as “Facade repairs including masonry replacement, terracotta replacement, terracotta patching and bulkhead railing installation as per plans filed. No change in use, egress or occupancy.”
- Alteration, filed Apr 22, 2022, estimated cost $21K, described as “Propose to remove existing partitions and put in new fire rated wall. No change to use, egress or occupancy.”
- Alteration, filed Mar 14, 2022, estimated cost $1K, described as “Installation of emergency sidewalk shed in accordance with nycc 2014 chapter 33 building code. No change in egress, use, or occupancy.”
- Alteration, filed Oct 22, 2018, estimated cost $3K, described as “Modification to existing Verizon telecommunications site. Replace 3 antennas on existing mounts on roof. All in conformance with TPPN 5/98. No change in use, egress, or occupancy.”

## Property taxes

- Assessment: $25,020,450
- 2026–27 tax: $2,634,700
- Market value (city estimate): $55,601,000
- Taxable value: $24,287,430
- Assessed land: $3,420,000
- Assessed improvements: $21,600,450

## Zoning

C6-2: floor area ratio 12.93 built, above the 6.02 base zoning allows, which bonuses, transfers or older rules can permit.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Landmarks

Part of Film Center Building (Interior Landmark). 50 Landmarks Preservation Commission permits are on file.

## Board and land use applications

- 630 Ninth Ave MN CB 4 Office Space (City Planning 2023M0330): Completed, filed Apr 13, 2023, decided Jun 1, 2023. An office space application to facilitate acquisition of approximately 1900 square feet of office space at 630 9th Avenue is being sought by DCAS and Manhattan CB 4 in Community District 4, Manhattan
- MARSIELLE (City Planning P2002M0433): Completed, decided Oct 31, 2001. NEW-UNENCLOSED SIDEWALK AVE WITH 60 SEATS
- JEZEBEL RESTAURANT (City Planning P2001M0538): Completed, decided Jan 29, 2001. NEW-UNENCLOSED SIDEWALK CAFE WITH 64 SEATS
- FILM CENTER BLDG INTERIOR (City Planning P1983M0315): Completed, decided Jan 13, 1983. LANDMARK-CITY COLLEGE OF NY, REMSEN CEMETERY,TROTTING\*COURSE LA; Additional LPC #(s): 317