Industrial · built 1962 · Block 1091, Lot 1.
Building permits
- Alteration, filed Aug 31, 2026, estimated cost $350K, described as “Herewith filing for Structural and General Construction repairs to this existing parking garage including temporary structural shoring. No change to use, occupancy or egress.”
- Alteration, filed Mar 2, 2026, estimated cost $100K, described as “Extension of existing mechanical floor using new concrete slab bearing walls and foundation. * no change in egress use or exceed occupancy use. * occupancy of the spaces during construction shall not be construed as anacceptance of such…”
- Alteration, filed Feb 21, 2026, estimated cost $8K, described as “Proposed installation of temporary pipe scaffold as per plans. Work shall comply with chapter #33 of the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Oct 2, 2023, estimated cost $759K, described as “Herewith filing repairs to existing parking garage. No change to use, occupancy or egress.”
- Alteration, filed Jun 8, 2023, estimated cost $88K, described as “Renovation of locker room area in the cellar. No change to use, egress or occupancy.”
- Alteration, filed Mar 10, 2022, estimated cost $107K, described as “Install chimney liner.”
- Alteration, filed Jan 21, 2022, estimated cost $15K, described as “Replacement of fixed windows to operable windows at specified locations on the Second, Third and Fourth floors. No change of use, egress or occupancy.”
- Alteration, filed Jan 20, 2022, estimated cost $160K, described as “Mechanical work in the cellar and 1ST floor as per plans filed herewith. Mechanical work includes removal of ductwork, install new metal ductwork, supports, registers, volumedampers. No change to use, egress, or occupancy.”
- Alteration, filed Sep 2, 2021, estimated cost $5K, described as “Installation of pipe scaffolding as per plans, pipe scaffolding shall comply with chapter # 33 of the 2014 code. No change in use egrees or occupancy under this application.”
- Alteration, filed Aug 19, 2021, estimated cost $5K, described as “Installation of construction fence as per plans. Construction fence shall comply with chapter #33 of the 2014 code. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 13, 2021, estimated cost $5K, described as “Installation of 300psf sidewalk shed as per plans. Sidewalk shed shall comply with chapter #33 of the 2014 code no change to use, egress or occupancy.”
- Alteration, filed Aug 17, 2020, estimated cost $600K, described as “Install 2 new gas fired tank water heaters and separate storage tank”
- Alteration, filed Aug 7, 2020, estimated cost $50K, described as “Structural modification to distribution facility as shown on drawings filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Jul 20, 2020, estimated cost $35K, described as “Mechanical modification to distribution facility as shown on drawings filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Aug 21, 2019, estimated cost $5K, described as “Installation of sidewalk shed as per plans. Sidewalk shed live load 300 psf shall comply with chapter #33 of the 2014 code no change to use, egress or occupancy under this application.”
- Alteration, filed Mar 22, 2019, described as “Installation of sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jul 24, 2018, described as “Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
Property taxes
- Assessment
- $40,848,750
- 2026–27 tax
- $4,315,256
- Market value (city estimate)
- $90,775,000
- Taxable value
- $39,779,280
- Assessed land
- $11,232,900
- Assessed improvements
- $29,615,850
Zoning
M2-4: floor area ratio 5.99 built, above the 5.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard. FEMA’s preliminary map: zone X, moderate risk: a 0.2% chance of flooding each year.