12 West 72nd Street, Manhattan
Co-op · 152 units · built c. 1927 · Block 1124, Lot 42.
Building permits
- Alteration, filed Sep 16, 2026, described as “Suspended Scaffold for Facade Restoration & Inspection as Shown on Plans”
- Alteration, filed Aug 24, 2026, estimated cost $50K, described as “Miscellaneous Facade Repairs.”
- Alteration, filed May 1, 2026, estimated cost $208K, described as “Renovations to apt 19A as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jan 7, 2026, described as “FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Starrett Merchant”
- Alteration, filed Dec 19, 2025, estimated cost $100K, described as “Filing to show an apartment combo/renovation of apartment 10BC and 10D”
- Alteration, filed Nov 12, 2025, estimated cost $118K, described as “Renovation of an existing apartment# 20A on the 20th floor. Work includes non-structural demolition, general construction and installation of new kitchen exhaust as per plans filed herewith. no change to use, egress or occupancy.”
- Alteration, filed Sep 29, 2025, estimated cost $35K, described as “Interior and exterior renovation work as per plans filed herewith. No change to use, egress, or occupancy.”
- Alteration, filed Jun 10, 2025, estimated cost $76K, described as “Interior general construction of apt 12A as shown herewith. No changes to egress, occupancy or use.”
- Alteration, filed Jun 6, 2025, estimated cost $50K, described as “Filing for general construction work as per plans showing interior renovations”
- Alteration, filed Jun 3, 2025, estimated cost $17K, described as “Herewith filing General Construction in conjunction with Bathroom renovation in apartment 15EF. No change in use, egress or occupancy is proposed.”
- Alteration, filed May 7, 2025, estimated cost $60K, described as “Interior renovation of existing apartment”
- Alteration, filed Dec 22, 2023, described as “FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS, SEE ATTACHED PLANS Designated Primary Site supervisor: Kenneth Cole”
- Alteration, filed Dec 15, 2023, described as “Material Hoist”
- Alteration, filed Jul 10, 2023, estimated cost $35K, described as “Filing for window openings on 17TH floor as per plans filed herewith. No change in egress, use or occupancy.”
- Alteration, filed Sep 27, 2022, estimated cost $5K, described as “Installation of ac unit for apt. 30A as per plans filed herewith. No change to use, egress or occupancy”
- Alteration, filed Aug 24, 2022, estimated cost $5K, described as “Structural work for fireplace at the apt. 30A as per plans filed herewith.”
- Alteration, filed Jul 27, 2022, estimated cost $272K, described as “Exterior repairs of cupola and facade alteration as per plans filed herewith. No change to use, egress, or occupancy.”
- Alteration, filed Apr 26, 2022, estimated cost $5K, described as “Installation of 300 psf sidewalk shed, stair tower and pipe scaffolding as per plans. All equipment shall comply with chapter #33 of the 2014 code. No change in use, egress or occupancy under this application.”
- Alteration, filed Mar 21, 2022, estimated cost $30K, described as “Modifications to interior ductwork”
- Alteration, filed Mar 17, 2022, estimated cost $222K, described as “Interior renovations to unit 15 ABC”
- Alteration, filed Mar 17, 2022, estimated cost $53K, described as “Interior plumbing renovations to unit 15ABC”
- Alteration, filed Sep 1, 2021, estimated cost $28K, described as “Plumbing fixtures modifications for apt. 10F as per plans filed herewith.”
- Alteration, filed Sep 1, 2021, estimated cost $410K, described as “Renovation of existing duplex on 9TH & 10TH floor. Work includes modification of interior partitions, doors,floors, ductwork for new centralac system. No change to use, egress or occupancy.”
- Alteration, filed Aug 3, 2020, estimated cost $16K, described as “Modification to existing plumbing fixtures as per plans filed herewith. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 3, 2020, estimated cost $24K, described as “Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.”
1 more, older permit is in this building’s full list on the map.
Property taxes
- Assessment
- $30,207,150
- 2026–27 tax
- $2,911,241
- Market value (city estimate)
- $67,127,000
- Taxable value
- $26,790,818
- Assessed land
- $3,649,950
- Assessed improvements
- $26,557,200
Tax breaks
- Co-op and condo abatement, with no end date, a $422,540 credit this tax year.
Zoning
R10A: floor area ratio 18.85 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Recent sales
- Jul 17, 2026: $735,000
- Jul 9, 2026: $4,250,000
- Oct 8, 2025: $383,000
- Aug 13, 2025: $3,600,000
- Jun 12, 2025: $1,100,000
- May 14, 2025: $985,000
- Feb 24, 2025: $2,325,000
- Jan 29, 2025: $748,000
- Jan 17, 2025: $6,000,000
- Apr 26, 2024: $685,000
The 10 most recent of 56 open-market sales since 2016, from the Department of Finance’s sales files.
Landmarks
Part of Upper West Side/Central Park West Historic District (Historic District). 50 Landmarks Preservation Commission permits are on file.