145 West 67th Street, Manhattan
Apartment building · 450 units · built 1986 · Block 1139, Lot 1.
Building permits
- Alteration, filed Jun 12, 2024, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Jun 6, 2024, described as “Installation of suspended scaffold for facade work or inspection. Amend #1, change in outrigger beam layout.”
- Alteration, filed May 21, 2024, estimated cost $750K, described as “Exterior restoration including concrete repairs; masonry reconstruction, crack & spall repairs; sealant replacement, metal repainting & roof replacement.”
- Alteration, filed Sep 23, 2022, estimated cost $15K, described as “Interior renovation to existing store at first floor , construct new partitions . All as per plan .no change in use egrees or occupancy”
- Alteration, filed Sep 7, 2022, estimated cost $20K, described as “Installation of plumbing fixtures as per plans submitted herewith. Work in conjunction with application #140979074. No change to use egress or occupancy under this application”
- Alteration, filed Jul 25, 2022, estimated cost $100K, described as “Repair of garage at cellar and sub cellar level , all as per plan . no change in use egress or occupancy..”
- Alteration, filed Jan 26, 2022
- Alteration, filed May 4, 2021, estimated cost $10K, described as “Installation of new plumbing fixtures for new handicapped toilet for retail store renovation. No change in egress use or occupancy.”
- Alteration, filed May 4, 2021, estimated cost $90K, described as “Renovation of existing store on ground (first) floor. New non-bearing interior partitions, Architectural finishes, ceilings, new supplemental air conditioning system. No change to egress use or occupancy.”
- Alteration, filed Feb 18, 2020, estimated cost $3K, described as “Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
Property taxes
- Assessment
- $81,740,250
- 2026–27 tax
- $9,370,926
- Market value (city estimate)
- $181,645,000
- Taxable value
- $75,335,046
- Assessed land
- $15,480,000
- Assessed improvements
- $66,260,250
Zoning
C4-7: floor area ratio 18.85 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- TOWER 67 (City Planning P1988M0704): Completed, decided Feb 14, 1991. 88-067M: VAR. FOR PROPOSED SUBSTITUTION OF A PHYSICAL CULTURE ESTABLISHMENT IN PLACE OF 60 EXISTING GARAGE SPACES IN A 158-CAR-GARAGE
- TOWER 67 (City Planning P1984M0837): Completed, decided May 14, 1986. 84-098M: PROPOSED 238 CAR GARAGE AS PART OF AN AS-OF-RIGHT MIXED USE PROJECT
- 149-51 E67ST, 154 E67 ST, 157-59 E67 ST, 163 E67 S (City Planning P1980M0705): Completed, decided Jun 12, 1980. LANDMARK-CITY COLLEGE OF NY, REMSEN CEMETERY,TROTTING*COURSE LA; Additional LPC #(s): 137