# 1995 Broadway, Manhattan

Condominium · built 1974 · Block 1139, Lot 7502.

On Umarelli: https://umarelli.org/nyc/1011397502/1995-broadway

More construction in Upper West Side: https://umarelli.org/nyc/manhattan/upper-west-side.md

Every lot on block 1139: https://umarelli.org/nyc/manhattan/1139.md

## Building permits

- Alteration, filed Jun 17, 2026, estimated cost $75K, described as “Interior renovation to existing bathrooms, provide new ADA bathroom on the 11 floor as per plans filed no change in use occupancy or egress”
- Alteration, filed May 26, 2026, estimated cost $106K, described as “Interior buildout of tenant space on portion of the 9 floor as per plans filed no change in use occupancy or egress”
- Alteration, filed May 5, 2026, estimated cost $503K, described as “Provide partitions ceiling and finishes for Interior renovation of existing office space on the 15 floor (marketed as 16) as per plans filed no change in use occupancy or egress”
- Alteration, filed Apr 13, 2026, estimated cost $40K, described as “Interior renovation to existing bathrooms, provide new ADA bathroom and demising wall on the 9 floor as per plans filed no change in use occupancy or egress”
- Alteration, filed Jan 23, 2026, estimated cost $60K, described as “Provide new duct layout changes to the existing HVAC system in conjunction with Alt # M01343640 as per plans filed”
- Alteration, filed Jan 22, 2026, estimated cost $33K, described as “Provide sanitary facilities in conjunction with Alt # M01343640 as per plans filed. No change in Use occupancy or egress”
- Alteration, filed Jan 22, 2026, estimated cost $53K, described as “Provide sprinkler heads on existing system in conjunction with Alt #M01343640 as per plans filed no change in use occupancy or egress”
- Alteration, filed Jan 14, 2026, estimated cost $95K, described as “Replacement of the damaged bricks and concrete patching.”
- Alteration, filed Jan 8, 2026, estimated cost $130K, described as “Interior renovation of existing office space, partitions and drop ceilings on the 14 floor (14 fl marketed as 15) as per plans filed no change in use occupancy or egress”
- Alteration, filed Dec 4, 2025, estimated cost $95K, described as “Replacement of the damaged bricks and concrete patching.”
- Alteration, filed Dec 1, 2025, estimated cost $60K, described as “Removal of non load bearing gyp. bd. partitions and drop ceilings on the 9, 11 & 15 floor (15 fl marketed as 16) as per plans filed no change in use occupancy or egress”
- Alteration, filed Nov 6, 2025, estimated cost $25K, described as “Provide changes to the existing HVAC system in conjunction with Alt # M01295367 as per plans filed”
- Alteration, filed Oct 27, 2025, estimated cost $6K, described as “Provide sanitary facilities in conjunction with Alt # M01295367 as per plans filed. No change in Use occupancy or egress”
- Alteration, filed Oct 27, 2025, estimated cost $21K, described as “Provide sprinkler heads on existing system in conjunction with Alt # M01295367 as per plans filed no change in use occupancy or egress”
- Alteration, filed Oct 20, 2025, estimated cost $48K, described as “Interior renovation of existing office space on portion of the 8th floor as per plans filed no change in use occupancy or egress”
- Alteration, filed Sep 11, 2025, estimated cost $45K, described as “Provide changes to the existing HVAC system in conjunction with Alt # M01259593 as per plans filed”
- Alteration, filed Aug 13, 2025, estimated cost $10K, described as “Provide sanitary facilities in conjunction with Alt # M01259593 as per plans filed. No change in Use occupancy or egress”
- Alteration, filed Aug 13, 2025, estimated cost $16K, described as “Provide sprinkler heads on existing system in conjunction with Alt # M01259593 as per plans filed no change in use occupancy or egress”
- Alteration, filed Jul 22, 2025, estimated cost $67K, described as “Interior renovation of existing office space on portion of the 8th floor as per plans filed no change in use occupancy or egress”
- Alteration, filed Jul 5, 2024, estimated cost $155K, described as “Mechanical work associated with the renovation of an existing office. There is no change proposed to use, egress, or occupancy.”
- Alteration, filed May 16, 2024, estimated cost $20K, described as “Plumbing work associated with the renovation of an existing office. There is no change proposed to use, egress, or occupancy.”
- Alteration, filed May 13, 2024, estimated cost $78K, described as “Sprinkler work associated with the renovation of an existing office. There is no change proposed to use, egress, or occupancy whatsoever.”
- Alteration, filed Apr 9, 2024, estimated cost $400K, described as “Proposed work to replace existing cooling tower and indoor water-cooled heat pump serving existing bank. Install new dx cooling split system. Existing air distribution ductwork to remain.”
- Alteration, filed Mar 1, 2024, estimated cost $389K, described as “General construction work associated with the renovation of an existing office There is no change proposed to use, egress, or occupancy.”
- Alteration, filed Nov 30, 2022, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”

12 more, older permits are in this building’s full list on the map: https://umarelli.org/nyc/1011397502/1995-broadway.

## Property taxes

- Assessment: $20,505,585
- 2026–27 tax: $2,087,134
- Market value (city estimate): $45,567,967
- Taxable value: $19,422,087
- Assessed land: $4,063,950
- Assessed improvements: $16,441,635
- Condo units with their own tax lots: 2

## Zoning

C4-7: floor area ratio 11.19 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology