4 Amsterdam Avenue, Manhattan
Condominium · 381 units · built 1991 · Block 1151, Lot 7501.
Building permits
- Alteration, filed Oct 22, 2026, estimated cost $13K, described as “Repair to parking garage as per plans. No change in use, occupancy or egress under this application.”
- Alteration, filed Jun 28, 2023, estimated cost $85K, described as “New gas meter room. No change in means of egress use group or occupancy.”
- Alteration, filed Jun 27, 2023, estimated cost $45K, described as “Provide new exhaust fan, tie to existing ductwork. Provide new elevaotr machine room air conditioner units. Replace existing air-cooled corridor bentialation unit with new.”
- No Work, filed Sep 29, 2022
- Alteration, filed Sep 21, 2022, estimated cost $15K, described as “Change in use to partial 1st floor retail space to Eating and Drinking Establishment.”
- Alteration, filed Jun 16, 2022, estimated cost $360K, described as “Install (1) new 7/10 gage stainless steel chimney liner in existing van packer concrete chimney. No change in means of egress, use group or occupancy.”
- Alteration, filed Sep 22, 2021, estimated cost $11K, described as “Installation of temporary overhead protection in the lobby per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Sep 13, 2021, described as “Installation of supported scaffold as shonw on drawings. No change in use egress or occupancy. We shall comply with chapter 33 of 2014 b.c”
- Alteration, filed Apr 14, 2021, estimated cost $800K, described as “Spall patching and brick masonry repairs as per plans. No change to use, egress, or occupancy.”
- Alteration, filed Mar 31, 2021, estimated cost $299K, described as “Filing herewith application for HVAC modifications as per drawings submitted. No change in use, egress or occupancy.”
- Alteration, filed Mar 11, 2021, described as “28-105.4.1 emergency work- installation of sidewalk shed as shown on drawing to protect pedestrians from falling debris. No change in use egress oroccupancy. We shall comply with chapter 33 of 2014 b.c”
- Alteration, filed Aug 13, 2020, estimated cost $78K, described as “Modification to Sprinkler heads in Cellar and on 1st Floor as per plans. This modification in conjunction with ALT 1 Application # 140928165. This application to be professionally certified.”
- Alteration, filed Aug 13, 2020, estimated cost $35K, described as “Modification to plumbing fixtures in subcellar, cellar and on 1st floor as per plans. This filing in conjunction with ALT1 application # 140928165. This application to be professionally certified.”
- Alteration, filed Aug 13, 2020, estimated cost $150K, described as “Modification to duct work and installation of condensing units as per plans. This application filed in conjunction with ALT1 #140928165. This application to be professionally certified.”
- Alteration, filed Jun 12, 2020, estimated cost $6K, described as “Modifications of plumbing fixtures on the 11th Floor (Apt. 1108 & 1109) as per plans filed. No change to use, egress or occupancy is involved.”
Property taxes
- Assessment
- $55,349,133
- 2026–27 tax
- $4,844,692
- Market value (city estimate)
- $122,998,074
- Taxable value
- $39,218,776
- Assessed land
- $8,856,449
- Assessed improvements
- $46,492,684
- Condo units with their own tax lots
- 4
Tax breaks
- Nonprofit exemption (hospital staff housing), with no end date, about $1,584,889 a year below the full tax.
Zoning
C4-7: floor area ratio 11.96 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- OLYMPIC FLAME DINER - RENEWAL (City Planning P2017M0457): Completed, decided Apr 12, 2018. Renewal application by Heledona, Inc., d/b/a, Olympic Flame Diner for a revocable consent to operate an existing enclosed sidewalk café with *11 tables and *32 seats at 200 West 60th Street on the southwest corner of Amsterdam Avenue…
- OLYMPIC FLAME DINER (Renewal) (City Planning P2014M0086): Completed, decided Feb 25, 2015. RENEWAL FOR 32 SEATS
- OLYMPIC FLAME DINER (City Planning P2012M0463): Completed, decided Dec 18, 2012. RENEWAL, ENCLOSED WITH 60 SEATS
- ST LUKE'S ROOSEVELT HOSPITAL CENTER (City Planning P2008M0051): Completed, decided Oct 25, 2012. 1ST MOD OF THE RESTRICTIVE DECL TO ALLOW IN THE EVENT OF*BANKRUPTCY OR FORECLOSURE REMOVAL OF THE RESTRICTION TO*HOSPITAL RELATED USES
- OLYMPIC FLAME DINER (City Planning P2010M0276): Completed, decided Mar 30, 2010. RENEWAL-ENCLOSED CAFE WITH 32 SEATS
- HELEDONA (City Planning P2006M0511): Completed, decided Sep 14, 2006. RENEWAL-ENCLOSED SIDEWALK CAFE WITH 32 SEATS
- OLYMPIC FLAME DINER (City Planning P2000M0483): Completed, decided Jun 19, 2000. RENEWAL-ENCLOSED SIDEWALK CAFE FOR 5-YEARS, WITH 32 SEATS
- HELEDONA (City Planning P1998M0692): Completed, decided Sep 9, 1998. NEW-ENCLOSED SIDEWALK CAFE WITH 32 SEATS
- THE CONCERTO A/KA BRODSKY WEST (City Planning P1992M0262): Completed, decided Aug 5, 1992. 1ST MODIFICATION TO ALLOW THE UNITS, IN THE EVENT OF FORE-*CLOSURE TO BE OCCUPIED BY EMPLOYEES IN ANY HOSPITAL IN NYC*WITH SPECIFIED FAMILY INCOME LEVELS
- THE CONCERTO A/K/A BRODSKY WEST (City Planning P1992M0109): Completed, decided Nov 1, 1991. FOLLOW-UP FOR A CERT TO THE NYC DEPT OF BLDGS FOR COMPLETION*OF THE OPEN SPACE & TREE PLANTING (POPS)