- Alteration, filed Jun 8, 2026, estimated cost $1K, described as “Installation of temporary pipe scaffold as per plan. No change in use, egress or occupancy.”
- Alteration, filed Mar 19, 2026, estimated cost $600K, described as “Herewith filing architectural work as per plans. No change in use, egress or occupancy”
- Alteration, filed May 20, 2025, estimated cost $100K, described as “Exterior work: replacement of existing storefront entry and canopy cladding at 3 west 92 street as per plans.”
- Alteration, filed Mar 7, 2025, described as “Facade restoration. New outriggers. Inspection.”
- Alteration, filed Feb 5, 2025, estimated cost $14K, described as “Limited exterior repairs consisting of concrete patch repairs and facebrick replacement. No change in use, egress, or occupancy.”
- Alteration, filed Nov 11, 2024, estimated cost $3K, described as “Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Jun 21, 2024, estimated cost $1K, described as “Installation of temporary pipe scaffold as per plan. No change in use, egress or occupancy.”
- Alteration, filed Feb 29, 2024, estimated cost $4.3M, described as “Herewith filing alteration replacing the existing front vestibule, as well as adding a door to the rear facade”
Property taxes
- Assessment
- $8,607,150
- Market value (city estimate)
- $19,127,000
- Taxable value
- $0
- Assessed land
- $2,812,500
- Assessed improvements
- $5,794,650
Tax breaks
- Nonprofit exemption (school), with no end date, about $933,704 a year below the full tax.
Zoning
R7-2 (part of the lot is R10A): floor area ratio 2.98 built, 3.44 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Landmarks
Part of Upper West Side/Central Park West Historic District (Historic District). 14 Landmarks Preservation Commission permits are on file.
Board and land use applications
- Change to an earlier grant (Board of Standards and Appeals 30-99-BZIII): Change to an earlier grant, Granted, filed Jun 9, 2000, decided Oct 24, 2000. Remand
- Change to an earlier grant (Board of Standards and Appeals 30-99-BZII): Change to an earlier grant, Granted, filed Jun 9, 2000, decided Aug 8, 2000. Amendment-To permit a 3' setback along the western size of the proposed building from the third thru the fifth floors.
- 7TH AMENDED WEST SIDE URP (WSURP) (City Planning P2000M0199): Completed, decided Aug 2, 2000. AMEND THE URP TO FACILITATE EXPANSION OF COLUMBIA GRAMMAR*SCHOOL ON SITE 23A
- COLUMBIA GRAMMAR PREPARATORY_SCHL (City Planning P1983M0042): Completed, decided Jan 27, 1983. LDA-SITE 23A,23B