Building permits
- Alteration, filed Oct 23, 2026, estimated cost $350K, described as “Minor interior alteration and combination of (2) horizontally-adjacent units as per plans submitted herewith. Architectural and Mechanical work only under this application. No change in use, egress, or occupancy proposed under this…”
- Alteration, filed Feb 10, 2025, estimated cost $4K, described as “Proposed minor plumbing alteration to Apt. 3A, as per plans. No change to use, occupancy or egress under this application.”
- Alteration, filed Jul 17, 2024, estimated cost $105K, described as “Application filed to renovate apt 5F to include modification to non bearing partitions with new finishes as per the plans filed herewith no change to use, egress or occupancy”
- Alteration, filed Jan 15, 2024, estimated cost $355K, described as “Replace oil fired boiler with boiler and gas/oil burner. Change grade of oil from #4 to #2.”
- Alteration, filed Oct 24, 2023, estimated cost $3K, described as “Proposed installation of heavy duty sidewalk shed for remedial repairs as per plans. No change in use occupancy or egress under this application. Live load 300 per square feet. Sidewalk shed shall comply with chapter # 33 of the 2014 code.”
- Alteration, filed Mar 30, 2023, estimated cost $120K, described as “Herewith file plans to renovate apt. 11F. Minor removal and construction of partitions, replace bathroom and kitchen. No change to use egress or occupancy.”
- Alteration, filed Mar 30, 2023, estimated cost $28K, described as “Herewith file plans to renovate one bathroom and kitchen. No change to use egress or occupancy.”
- Alteration, filed Dec 10, 2021, estimated cost $5K, described as “Installation of interior partitions, ceilings, and doors.”
- Alteration, filed Dec 10, 2021, estimated cost $7K, described as “Installation of plumbing fixtures along with related piping.”
- Alteration, filed Jun 30, 2021, estimated cost $23K, described as “Interior renovation of existing store with partition work only at partial first floor. No change in use, means of egress, or occupancy.”
- Alteration, filed Mar 24, 2020, estimated cost $28K, described as “Hereby filing for the interior renovation of apt 8E located on the 8TH floor (plumbing work). No change to use occupancy or egress.”
- Alteration, filed Jan 15, 2020, estimated cost $20K, described as “Installation of split ac system in apartment #11AJ. Work to include in window condensing units; air handlers and related ductwork; and dryer and bathroom exhaust, as per plans filed herewith.”
- Alteration, filed Jan 10, 2020, estimated cost $58K, described as “Modification of plumbing system in apt. #11AJ, as per plans filed herewith.”
- Alteration, filed Sep 25, 2019, described as “Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
Property taxes
- Assessment
- $19,380,150
- 2026–27 tax
- $1,897,697
- Market value (city estimate)
- $43,067,000
- Taxable value
- $17,522,905
- Assessed land
- $2,686,500
- Assessed improvements
- $16,693,650
Tax breaks
- Co-op and condo abatement, with no end date, a $284,184 credit this tax year.
Zoning
C4-6A (part of the lot is R8): floor area ratio 11.14 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Recent sales
- Sep 23, 2026: $1,325,000
- Sep 15, 2026: $624,407
- Aug 20, 2026: $1,200,000
- Feb 17, 2026: $990,000
- Feb 17, 2026: $675,000
- Dec 18, 2025: $810,000
- Nov 19, 2025: $1,325,000
- Sep 26, 2025: $742,500
- Sep 9, 2025: $1,962,500
- Aug 6, 2025: $730,000
The 10 most recent of 56 open-market sales since 2016, from the Department of Finance’s sales files.