Building permits
- Alteration, filed Oct 30, 2024, estimated cost $5K, described as “Temporary system scaffold as per drawings. System scaffold shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Aug 7, 2024, estimated cost $1K, described as “BOILER FILING AS PER PLANS FILED filed in conjunction with NB: 121208095.”
- Alteration, filed Jul 16, 2024, estimated cost $3K, described as “Installation and use of mobile equipment, as per plans filed. No change in egres, use or occupancy.”
- Alteration, filed Jul 16, 2024, estimated cost $3K, described as “Installation and use of mobile equipment, as per plans filed. No change in egres, use or occupancy.”
- Alteration, filed Jul 16, 2024, estimated cost $3K, described as “Installation and use of mobile equipment, as per plans filed. No change in egres, use or occupancy.”
- Alteration, filed May 20, 2024, described as “Installation of temporary suspended scaffolds per plan submitted. Work shall comply with 2022 building code chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Apr 22, 2024, estimated cost $1K, described as “Installation of working platform in accordance with nycc 2022 chapter 33 building code. No change in egress, use, or occupancy.”
- Alteration, filed Feb 15, 2024, estimated cost $3K, described as “Temporary cantilevered overhead protection as per drawings during NB const, filed sep. Overhead protection shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Feb 15, 2024, estimated cost $3K, described as “Temporary cantilevered work platform as per drawings. Platform shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Jan 10, 2024, estimated cost $4K, described as “Use of mini crane during new building construction, filed separately under 121208095”
- Alteration, filed Nov 17, 2023, estimated cost $30K, described as “Heavy duty sidewalk shed during NB const, filed sep. Sidewalk shed shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application. Dot permits by others for shed installed on sidewalk/roadway”
- Alteration, filed Aug 30, 2023, estimated cost $20K, described as “Dual 7000 # capacity personnel/material hoists during NB const, filed sep. Hoists shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application. Elevator application submitted separately.”
- Alteration, filed Aug 30, 2023, estimated cost $20K, described as “Temporary hoist run-back structure during new bldg construction, filed separately. Hoist run-back structure shall comply with ch #33 of the NYC bldg code. No change in use, occupancy or egress under this application. Hoist & elevator appl…”
- Alteration, filed Dec 27, 2022, estimated cost $3K, described as “Installation of temporary roof protection at adjacent property (7 west 54 street) during NB const, filed sep. Roof protection shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application”
- Alteration, filed Apr 7, 2022, estimated cost $3K, described as “Installation of temporary construction fence as per drawings during NB const, filed sep. Construction fence shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application”
- Alteration, filed Mar 2, 2022, estimated cost $1K, described as “Install sprinkler standpipe as per plans filed.”
- Alteration, filed Jul 8, 2020, estimated cost $1K, described as “Temporary standpipe filed in conjunction with NB #121208095”
- Alteration, filed May 11, 2020, estimated cost $1K, described as “Mechanical work as per plans filed. Application filed in conjunction with new building 121208095.”
- Alteration, filed May 11, 2020, estimated cost $1K, described as “Plumbing work as per plans filed”
- Alteration, filed May 6, 2020, estimated cost $1K, described as “Structural work as per plans filed”
- Alteration, filed Feb 24, 2020, estimated cost $2K, described as “Installation of 8' plywood fence to protect site, at time of full demolition.”
- Alteration, filed Sep 10, 2019, described as “Proposed installation of temporary pipe scaffold as per plans. Work shall comply with chapter #33 of the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Sep 10, 2019, estimated cost $4K, described as “Proposed installation of heavy duty sidewalk shed as per plans. Live load 300 lbs per square feet. Sidewalk shed shall comply with chapter #33 of the NYC building code. No change in use, occupancy, or egress under this application.”
Property taxes
- Assessment
- $22,529,700
- 2026–27 tax
- $2,802,469
- Market value (city estimate)
- $50,066,000
- Taxable value
- $22,529,700
- Assessed land
- $3,701,250
- Assessed improvements
- $18,828,450
Zoning
C5-P: floor area ratio 13.67 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Recent sales
- Mar 5, 2019: $20,000,000
Open-market sales since 2016, from the Department of Finance’s sales files.
In the news