# 885 2nd Avenue, Manhattan

Commercial · built 1971 · Block 1321, Lot 22.

On Umarelli: https://umarelli.org/nyc/1013210022/885-2-avenue

More construction in Midtown East: https://umarelli.org/nyc/manhattan/midtown-east.md

Every lot on block 1321: https://umarelli.org/nyc/manhattan/1321.md

## Building permits

- Alteration, filed Nov 4, 2026, estimated cost $25K, described as “The scope of this project is interior build-out of tenant space including demo of existing construction, new construction and installation of partitions, floor and wall finishes, doors and light fixtures. No change in use, egress &…”
- Alteration, filed Sep 25, 2026, estimated cost $10.3M, described as “Removal and installation of non-load bearing walls, doors, floors, cieling and finishes. No change to use, egress or occupancy.”
- No Work, filed Sep 4, 2026, described as “Microsoft annual corporate meeting/cocktail hour”
- Alteration, filed Jul 27, 2026, estimated cost $800, described as “Sign tag as non-illuminate frabric flag w/ logo sign b x 2 flags @ 2ND avenue elevation "green back grpund whole foods market"”
- Alteration, filed Jul 27, 2026, estimated cost $1K, described as “Sign tag as non-illuminate chanel letter sign a-1 @ east 47TH street elevation "whole foods market daily shop"”
- Alteration, filed Jul 27, 2026, estimated cost $1K, described as “Sign tag as illuminate monument sign with three panelw/ vinyl grap sign f @ conner elevation "whole foods market "”
- Alteration, filed Jul 27, 2026, estimated cost $1K, described as “Sign tag as non-illuminate chanel letter sign a-2 @ 2ND avenue elevation "whole foods market daily shop"”
- No Work, filed Apr 24, 2026
- Alteration, filed Mar 27, 2026, estimated cost $207K, described as “The scope of this project is interior build-out of tenant space including demo of existing construction, new construction and installation of partitions, floor and wall finishes, doors and light fixtures. No change in use, egress &…”
- Alteration, filed Mar 4, 2026, estimated cost $1K, described as “Erection of construction fences at certain locations along first floor commercial storefront. No change to use, egress or occupancy.”
- No Work, filed Nov 10, 2025
- Alteration, filed Oct 10, 2025, estimated cost $30K, described as “Filing to remove and demolish (5) existing 60-ton chillers along with all associated piping, and installing (2) new 180-ton modular chiller banks along with all associated piping. No change to use, egress or occupancy.”
- Alteration, filed Oct 8, 2025, estimated cost $25K, described as “New 1 hour rated boiler room on modified equipment platform. Demolition of existing and installationof new storefront areas. No change to use, egress or occupancy.”
- No Work, filed Sep 4, 2025, described as “Microsoft annual corporate meeting/cocktail hour”
- Alteration, filed Jun 3, 2025, estimated cost $13K, described as “Installation of temporary construction plywood fence enclosure as per plans during construction. No change in use, egress or occupancy. Fence shall comply with chapter 33 of NYC building code of 2022.”
- Alteration, filed Apr 18, 2025, estimated cost $2.8M, described as “Interior build-out related to LA Fitness. No change in Use, Egress or Occupancy.”
- Alteration, filed Feb 20, 2025, estimated cost $3K, described as “Installation of a temporary material storage per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Feb 11, 2025, estimated cost $3K, described as “Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Nov 20, 2024, estimated cost $465K, described as “Filing to provide removal & replacement of non-load bearing partitions, ceiling, & interior finishes on the 2ND floor. No change to use, egress or occupancy.”
- Alteration, filed Nov 19, 2024, estimated cost $17K, described as “Partial demolition at first floor, cellar and subcellar levels. After demolition, installationof new partitions and doors are proposed. See plans, elevations & sections for additionalinformation and clarification. No change to use, egress…”
- Alteration, filed Nov 18, 2024, estimated cost $54K, described as “Second floor roof replacement as per plansubmitted herewith. There is no change in use, egress or occupancy.”
- Alteration, filed Nov 15, 2024, estimated cost $22K, described as “Filing application to erect illuminated & non-illuminated signs for club studio. No change in use, egress or occupancy.”
- Alteration, filed Nov 14, 2024, estimated cost $675K, described as “Partial floor tenant interior improvements to the 5TH floor of an existing 46 story building. Scope of work includes updating fixtures, equipment and finishes at the men's women's & ADA restrooms. No change to use, egress or occupancy.”
- Alteration, filed Sep 25, 2024, estimated cost $10K, described as “Partial demolition of existing storefront at first floor and cellar level. After demolition, installation of new storefront is proposed at the locations in which existing storefront was demolished. No change to use, egress or occupancy.”
- No Work, filed Sep 10, 2024, described as “Microsoft annual corporate meeting/cocktail hour”

58 more, older permits are in this building’s full list on the map: https://umarelli.org/nyc/1013210022/885-2-avenue.

## Property taxes

- Assessment: $115,739,550
- 2026–27 tax: $12,555,426
- Market value (city estimate): $257,199,000
- Taxable value: $115,739,550
- Assessed land: $33,075,000
- Assessed improvements: $82,664,550

## Zoning

C1-9 (part of the lot is R10): floor area ratio 19.73 built, above the 10.00 base zoning allows, which bonuses, transfers or older rules can permit.

## Recent sales

- Jun 5, 2026: $265,250,000, 805,467 sq ft ($329 per sq ft)
- Jan 8, 2019: $565,754,371

Open-market sales since 2016, from the Department of Finance’s sales files.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Board and land use applications

- Change to an earlier grant (Board of Standards and Appeals 218-06-BZII): Change to an earlier grant, Granted, filed May 1, 2017, decided Jul 24, 2018. Extension of Term of a previously approved Special Permit (§73-36) which permitted the operation of a Physical Cultural Establishment (New York Sports Club) located on the sub-cellar and cellar levels with an entrance on the first floor in…
- Variance or special permit (Board of Standards and Appeals 218-06-BZ): Variance or special permit, Granted, filed Aug 30, 2006, decided Feb 13, 2007. Special Permit (§73-36) to allow the operation of an existing PCE located on the sub-cellar and cellar levels with an entrance on the first floor in a 46-story commercial building. The Premises is located in C1-9 (TA), R8B, and R10 zoning…

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology