Building permits
- Alteration, filed Jun 4, 2026, estimated cost $496K, described as “Dividing classroom 114 into two rooms.”
- Alteration, filed Nov 21, 2025, estimated cost $10K, described as “Installation of temporary construction fence for ps 225M at 317 east 67 street, manhattan as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Oct 31, 2025, estimated cost $40K, described as “Repair two existing cellar level steel columns with concrete encasement and new concrete piers to the existing footing”
- Alteration, filed Jul 1, 2024, estimated cost $440K, described as “Interior renovation of existing classroom into fitness classroom. Renovate toilet. Replace interior finishes, interior doors, structural steel framing to support proposed RTU, toilet partitions and accessories.”
- Alteration, filed Sep 27, 2023, estimated cost $993K, described as “M480: Interior renovation of an existing school building including addition of two multipurpose fitness rooms and boys & girls shower rooms.”
- Alteration, filed Jun 29, 2023, estimated cost $8K, described as “Cover existing platform over hoist-way with steel plate, provide new concrete stair and aluminum railing, and install new steel grating for existing shaft vent.”
- Alteration, filed Jun 28, 2023, estimated cost $6K, described as “Cover existing platform over hoist-way with steel plate, install new stall grating for existing shaft vent, provide new stair, railing and new door”
- Alteration, filed Mar 24, 2023, estimated cost $15K, described as “Installation of chutes on various roof elevation to remove drbris from roofs to ground floor.”
- Alteration, filed Mar 10, 2023, estimated cost $6K, described as “Cover existing platform over hoistway with steel plate, install new stall grating for existing shaft vent, provide new stair, railing and new door. Remove and infill existing door opening at elevator a shaft in 5TH floor.”
- Alteration, filed Nov 16, 2022, estimated cost $10K, described as “Installation of construction fence on ground floor to protect the public from entering construction areas.”
- Alteration, filed Nov 16, 2022, estimated cost $25K, described as “Installation of supported scaffold on the facade of the school building and selected roofs to performe construction and repair work.”
- Alteration, filed Nov 15, 2022, estimated cost $10K, described as “Installation of sidewalk shed around school building to protect the public whlie construction and repair are performed on the roof and selected facade areas”
- Alteration, filed Jun 27, 2022, estimated cost $2.0M, described as “Replacement of existing exhaust fans and make-up air units.”
- Alteration, filed Mar 18, 2022, estimated cost $18.1M, described as “Roofing replacement, masonry repairs, parapet repairs and partial replacement, limited window and exterior door replacment, concrete wall, slab, and vault repairs at cellar, concrete paving replacement, and interior finish repairs.”
Property taxes
- Assessment
- $32,246,100
- Market value (city estimate)
- $71,658,000
- Taxable value
- $0
- Assessed land
- $14,490,000
- Assessed improvements
- $17,756,100
Zoning
R8B (part of the lot is C1-9): floor area ratio 3.53 built, 4.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.