# 417 East 68th Street, Manhattan

Community Facility Condominium · built 2003 · Block 1463, Lot 7501.

On Umarelli: https://umarelli.org/nyc/1014637501/417-east-68-street

More construction in Upper East Side: https://umarelli.org/nyc/manhattan/upper-east-side.md

Every lot on block 1463: https://umarelli.org/nyc/manhattan/1463.md

## Building permits

- Alteration, filed Dec 4, 2025, estimated cost $636K, described as “Hot water interconnection through underground tunnel connecting 1275 York Avenue and 417 East 68 Street as per plans. No change of use, occupancy or egress.”
- Alteration, filed Nov 20, 2025, estimated cost $400K, described as “Filing herewith for general construction as per the plans submitted. No change in egress, use or occupancy.”
- Alteration, filed Oct 22, 2025, estimated cost $205K, described as “Interior renovations in the sub-cellar. No change in occupancy, use or egress.”
- Alteration, filed Feb 6, 2025, estimated cost $2.3M, described as “Interior renovations on the 3rd floor. No change in occupancy, or egress.”
- Alteration, filed Dec 25, 2023, described as “FISP INSPECTION (Facade Inspection Safety Program) INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS SEE ATTACHED PLANS. Designated Primary Site supervisor: Kenneth Cole.”
- Alteration, filed Dec 6, 2023, estimated cost $152K, described as “Interior renovation in the sub-cellar. No change in occupancy, use or egress”
- Alteration, filed Nov 7, 2023, estimated cost $233K, described as “Interior renovations on the 7TH floor. No change in occupancy use or egress.”
- Alteration, filed Apr 6, 2023, estimated cost $110K, described as “Upsizing of existing exhaust fan motor and replacement of ductwork connections to the fan”
- Alteration, filed Sep 20, 2022, estimated cost $10K, described as “Installation of temporary trolley beam system as per drawings. Trolley beam shall complywith ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed May 11, 2022, estimated cost $15K, described as “Installation of temporary scaffold access tower as per drawings. Scaffold access tower shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed May 11, 2022, estimated cost $25K, described as “Installation of a 350# lifting capacity material only hoist system as per drawings. Hoist shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Jan 22, 2021, estimated cost $50K, described as “Filing for modifications to existing sprinkler system as per plans filed herewith. No change in use,egress or occupancy.”

## Property taxes

- Assessment: $153,049,500
- Market value (city estimate): $340,110,000
- Taxable value: $0
- Assessed land: $4,421,250
- Assessed improvements: $148,628,250
- Condo units with their own tax lots: 2

## Tax breaks

- Nonprofit exemption (hospital), with no end date, about $16,369,372 a year below the full tax.
- Nonprofit exemption (house of worship), with no end date, about $233,438 a year below the full tax.

## Zoning

R9 (part of the lot is R8): floor area ratio 27.96 built, above the 7.52 base zoning allows, which bonuses, transfers or older rules can permit.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Board and land use applications

- MSK Pavilion (City Planning 2022M0359): Special Permit, Zoning Map Change, Zoning Text Change, Authorization, Certification, Completed, filed Jan 23, 2024, decided Jul 24, 2025. This is a private application by MSK requesting a zoning map amendment from R8 to R9, text amendment to ZR 79-43, authorizations per ZR 79-21, a ZR 79-43 special permit, modifications to the Large Scale Community Facility Development and…

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology