# 503 East 74th Street, Manhattan

Utility · Block 1486, Lot 5.

On Umarelli: https://umarelli.org/nyc/1014860005/503-east-74-street

More construction in Upper East Side: https://umarelli.org/nyc/manhattan/upper-east-side.md

Every lot on block 1486: https://umarelli.org/nyc/manhattan/1486.md

## Building permits

- Alteration, filed Sep 2, 2026, described as “Installation of suspended scaffold for facade repair.”
- Alteration, filed Mar 5, 2026, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed May 19, 2025, described as “Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Jul 17, 2024, estimated cost $16K, described as “Replace two 5 ton air handlers in existing equipment room on 11th floor. Replace related condensers on the roof. No change in use, egress, or occupancy.”
- Alteration, filed Feb 6, 2024, estimated cost $340K, described as “Remove and replace roofing material in the areas noted on the drawings being submitted with this application, R - 25. Make additional associated repairs as required.”
- Alteration, filed Dec 19, 2023, estimated cost $30K, described as “Mechanical work in existing space filed in conjunction with DOB now sp. No change to use, occupancy or egress.”
- Alteration, filed Oct 27, 2023, estimated cost $1.5M, described as “Facade Repairs for Con Edison's East 74th Street Generating Station. No change to use, occupancy or egress.”
- Alteration, filed Jun 6, 2022, estimated cost $400K, described as “Con Edison's 74th Street Station facade repairs - as per drawings being submitted: T-001.00, T-002.00, G-001.00, G-002.00, G-003.00, A-101.00, A-102.00, A-202.00, A-201.00, A-203.00, A-301.00, A-302.00, A-303.00, A-304.00, A-305.00,…”
- Alteration, filed Mar 16, 2022, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Nov 18, 2020, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jun 1, 2020, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jan 30, 2018, estimated cost $37K, described as “Installation of heavy duty sidewalk shed during building alteration, filed separately. Sidewalk shed shall comply with chapter #33 of the NYC building code. No change in use, occupancy or egress under this application.”

## Zoning

M3-2: floor area ratio 0.00 built, 2.00 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology