# 950 Park Avenue, Manhattan

Co-op · 24 units · built c. 1920 · Block 1493, Lot 37.

On Umarelli: https://umarelli.org/nyc/1014930037/950-park-avenue

More construction in Upper East Side: https://umarelli.org/nyc/manhattan/upper-east-side.md

Every lot on block 1493: https://umarelli.org/nyc/manhattan/1493.md

## Building permits

- Alteration, filed Oct 1, 2025, estimated cost $200K, described as “Masonry opening changes at the third floor. No change to use, egress or occupancy. No change to use, egress or occupancy.”
- Alteration, filed Jul 11, 2025, estimated cost $300K, described as “Interior renovation of existing apartment 11B at the 11th floor as per plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Jun 20, 2025, estimated cost $420K, described as “Renovation of an existing apartment#12B on the 12th Floor. Work includes non-structural demolition and general construction as per plan filed herewith.”
- Alteration, filed Apr 23, 2025, estimated cost $69K, described as “Interior apartment renovations as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Nov 22, 2024, estimated cost $42K, described as “Interior renovation of apt. 10A. Removal of portions of non-load bearing partitions, removal of doors. New partitions, doors, lighting and finishes.”
- Alteration, filed Jul 24, 2024, estimated cost $40K, described as “Plumbing work filed in conjuction with interior renovation of unit 11B as per plans filed. No change in use. Egress or occupancy.”
- Alteration, filed Jul 24, 2024, estimated cost $140K, described as “Interior renovation of unit 11B. Replace in kind interior non load bearing partitions and related finishes as per plans filed. No change in use, egress or occupancy.”
- Alteration, filed May 17, 2023, estimated cost $400K, described as “Interior renovation to apartment 3A as per proposed plans submitted. No change to use, egress or occupancy.”
- Alteration, filed May 17, 2023, estimated cost $15K
- Alteration, filed Mar 16, 2023, described as “Installation of temporary pipe scaffold as per plans. No change in use, egress or occupancy.”
- Alteration, filed Feb 10, 2023, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Feb 7, 2023, estimated cost $45K, described as “Plumbing work for doctor's office unit 1GL: remove existing fixtures and install new fixtures as per plans filed. No change in use, egress or occupancy.”
- Alteration, filed Feb 7, 2023, estimated cost $145K, described as “Installation of mechanical system: a/c units, airhandlers, ducts, bathroom exhaust as per plans filed. No change in use, egress or occupancy.”
- Alteration, filed Feb 3, 2023, estimated cost $215K, described as “Renovate existing medical office 1GL: remove non-load bearing partitions, drop ceiling andfloor finishes.install new non-load bearing partitions, flooring finishes, ceilings and millwork as per plans filed. No change in use, egress or…”
- Alteration, filed Nov 22, 2022, estimated cost $341K, described as “Hereby filing facade restoraton as per plans”
- Alteration, filed Apr 25, 2022, estimated cost $24K, described as “Mechanical work filed in conjunction with renovation of an existing apartment on the sixth floor.”
- Alteration, filed Mar 31, 2021, estimated cost $40K, described as “Modification of plumbing works for interior renovation of apartment 8A as per plans filed herewith. Filed in conjuction with general construction application M00466925. No change in occupancy, egress, or use.”
- Alteration, filed Mar 31, 2021, estimated cost $380K, described as “Interior renovation of apartment 8A as per plans filed herewith. Filed in conjunction with plumbing application M00466987. No change in occupancy, egress, or use.”
- Alteration, filed Jan 8, 2020, estimated cost $6K, described as “Interior renovation to the existing doctor office, Unit Office SE. No change in use in use, egress, or occupancy.”
- Alteration, filed Jan 8, 2020, estimated cost $10K, described as “Interior renovation to the existing doctor office, Unit Office SE. No change in use in use, egress, or occupancy.”
- Alteration, filed Mar 14, 2018, described as “Installation of pipe scaffold as per plans. No change in use, egress or occupancy.”
- Alteration, filed Mar 12, 2018, described as “Installation of heavy duty sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed Feb 9, 2018, estimated cost $5K, described as “Installation of pipe scaffold as per plans.”
- Alteration, filed Feb 9, 2018, estimated cost $6K, described as “Installation of sidewalk shed as per plans.”

## Property taxes

- Assessment: $15,217,200
- 2026–27 tax: $1,499,409
- Market value (city estimate): $33,816,000
- Taxable value: $13,828,770
- Assessed land: $1,975,500
- Assessed improvements: $13,241,700

## Tax breaks

- Co-op and condo abatement, with no end date, a $220,752 credit this tax year.

## Zoning

R10: floor area ratio 9.88 built, 10.00 allowed by base zoning.

## Recent sales

- Aug 19, 2026: $5,700,000
- Apr 3, 2025: $7,300,000
- Oct 29, 2024: $8,350,000
- Oct 10, 2024: $5,500,000
- May 9, 2024: $8,200,000
- Aug 9, 2022: $1,820,000
- Apr 4, 2022: $8,800,000
- Mar 30, 2022: $10,850,000
- Dec 2, 2020: $4,200,000, Apt 8A
- Aug 22, 2019: $850,000

The 10 most recent of 12 open-market sales since 2016, from the Department of Finance’s sales files.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Landmarks

Part of Park Avenue Historic District (Historic District). 41 Landmarks Preservation Commission permits are on file.