320 East 94th Street, Manhattan
Commercial · built 1968 · Block 1556, Lot 40.
Building permits
- Alteration, filed Oct 14, 2026, estimated cost $37K, described as “Mount sinai - star center early demo floor 4TH floor - interior demo associated with general construction plans filed herwith. No chnage in use, egress or occupancy.”
- Alteration, filed Sep 28, 2026, estimated cost $2.5M, described as “Mount sinai - star center early demo floor 5TH floor - interior demo associated with general construction plans filed herwith. No chnage in use, egress or occupancy.”
- Alteration, filed Feb 5, 2026, described as “Suspended Scaffold for Facade Restoration as Shown on Plans”
- Alteration, filed Jan 20, 2026, estimated cost $1.8M, described as “Main Roof and setback roofs replacement and facade repairs No change in egress, use and occupancy.”
- Alteration, filed Nov 17, 2025, described as “Installation of temporary pipe scaffold as per plans. No change in use, egress or occupancy.”
- Alteration, filed Nov 17, 2025, estimated cost $4K, described as “Installation of temporary betamax hoist as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jul 18, 2024, described as “Installation of temporary sidewalk shed as per plans. No change in use, egress or occupancy.”
- Alteration, filed May 31, 2022, estimated cost $20K, described as “Renovation work in medical center cellar mechanical boiler room with new equipment, piping for flood mitigation purposes. No change in use, occupancy or egress.”
- Alteration, filed May 31, 2022, estimated cost $25K, described as “Installation of a linear trench system and the construction of a sump pit located in the mechanical room at the cellar floor of an existing 5 story commercial building.”
- Alteration, filed Jan 31, 2022, estimated cost $50K, described as “Installation of new chimney liner, including all the mechanical work required, and delivery of equipment.”
- Alteration, filed Jan 31, 2022, estimated cost $50K, described as “Replacement of existing boiler and hot water heater with three (3) new condensing boilers and two (2) domestic hot water heaters with associated devices.”
- Alteration, filed Jan 31, 2022, estimated cost $75K, described as “Replacement of existing boiler and hot water heater with three (3) new condensing boilers and two (2) indirect water heaters with associated devices.”
- Alteration, filed Aug 27, 2020, estimated cost $100K, described as “This application is being filed for the installation of two a/c units”
Property taxes
- Assessment
- $6,833,700
- Market value (city estimate)
- $15,186,000
- Taxable value
- $0
- Assessed land
- $1,584,000
- Assessed improvements
- $5,249,700
Tax breaks
- Nonprofit exemption (hospital staff housing), with no end date, about $741,320 a year below the full tax.
Zoning
C8-4: floor area ratio 4.50 built, 5.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- 19TH PRECINCT (City Planning P1986M0566): Completed, decided Apr 9, 1987. 86-277M: LEASE FOR 4 YRS BEGINNING 4/15/86 FOR GROUND & 2ND FLOORS BL1556. LT40.