- Alteration, filed Sep 1, 2026, described as “Ira for the vertical cable tray location inspection”
- Alteration, filed Sep 8, 2025, estimated cost $3.5M, described as “Application to be reviewed with the Development HUB. Site yard work and new 8'-0" high aluminum fence as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed Sep 5, 2025, estimated cost $2.2M, described as “Application to be reviewed with the Development HUB. Site Yard work and new 8'-0" high aluminum fence as per plans filed herewith. No change to use, egress or occupancy.”
- Alteration, filed May 10, 2024, described as “IRA for vertical conduit inspection”
- Alteration, filed Apr 22, 2024, estimated cost $30K, described as “Excavate to prepare trench for new gas service installation. Backfill trench and restore grass or concrete pavement.”
- Alteration, filed Apr 22, 2024, estimated cost $8K, described as “Excavate to prepare trench for new gas service installation. Backfill trench and restore grass or concrete pavement.”
- Alteration, filed Apr 22, 2024, estimated cost $8K, described as “Excavate to prepare trench for new gas service installation. Backfill trench and restore grass or concrete pavement.”
- Alteration, filed Apr 22, 2024, estimated cost $10K, described as “Excavate to prepare trench for new gas service installation. Backfill trench and restore grass or concrete pavement.”
- Alteration, filed Dec 5, 2023, estimated cost $38K, described as “Dish: Installation of new telecommunication antenna sectors, GPS antenna and equipment cabinet on the roof. Installation of conduits and service room connection as per plans. All work is in compliance with 5/98. No change in use, egress or…”
- Alteration, filed Jul 18, 2023, estimated cost $120K, described as “Replacing existing underground steam and condensate return piping with new between Bldg #9 and Bldg#14 as per plans filed herewith.”
- Alteration, filed Jul 12, 2018, estimated cost $2K, described as “Replacement of at&t antennas with related rrh units on the roof. All in conformance with tppn 5/98. No change in use, egress, or occupancy.”
Property taxes
- Assessment
- $23,227,200
- Market value (city estimate)
- $51,616,000
- Taxable value
- $0
- Assessed land
- $5,849,100
- Assessed improvements
- $17,378,100
Zoning
R7-2: floor area ratio 1.07 built, 3.44 allowed by base zoning.
Flood zone
Current FEMA flood map: zone AE, high risk: a 1% chance of flooding each year, base flood elevation 13 ft (NGVD29). FEMA’s preliminary map: zone X, moderate risk: a 0.2% chance of flooding each year.