820 Amsterdam Avenue, Manhattan
Apartment Building · 159 units · built 1964 · Block 1872, Lot 29.
Some of the city’s records for this lot were still loading when this page was made; it refreshes within minutes.
Building permits
- Alteration, filed Aug 20, 2026, described as “FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola”
- Alteration, filed Apr 21, 2026, described as “Suspended scaffold out rigger installation for facade inspection”
- Alteration, filed May 30, 2025, described as “Installation of suspended scaffold for roof replacement & rooftop structure renovation. Suspended scaffold shall comply with chapter 33 of the 2022 NYC building code. No change in use, egress or occupancy under this application.”
- Alteration, filed Dec 11, 2024, described as “Installation of material hoist for roof replacement & rooftop structure renovation. Material hoist shall comply with chapter 33 of the 2022 NYC building code. No change in use, egress or occupancy under this application.”
- Alteration, filed Dec 10, 2024, estimated cost $15K, described as “Installation of temporary chain link fence as per plans. Chain link fence shall comply with chapter 33 of the 2022 NYC building code. No change in use, egress or occupancy under this application.”
- Alteration, filed Dec 10, 2024, estimated cost $164K, described as “Installation of temporary sidewalk shed as per plans. Sidewalk shed shall comply with chapter 33 of the 2022 NYC building code. No change in use, egress or occupancy under this application.”
- Alteration, filed Sep 12, 2024, estimated cost $2.1M, described as “Exterior Roofing & Railing repairs: Removal/replacement/repairs of existing roofing membrane, flashing, roof deck, bulkhead door, sealant, spalled/cracked concrete, sheet metal, pavers. spandrel beams/balconies and drains. Install guard…”
- Alteration, filed Mar 18, 2022, estimated cost $5K, described as “Installation of 300psf sidewalk shed and pipe scaffoldin as per plans. All equipment shall comply with chapter # 33 of the 2014 code. No change in use occupancy or egress under this application.”
- Alteration, filed Feb 7, 2022, estimated cost $17.8M, described as “Nycha boiler -amsterdam house- remove existing boiler room equipment install new indoor heating/cooling units, vrf condensing units and rooftop equipment dunnage as per plans. Demolish existing door, install new door. No change in use,…”
- Alteration, filed Feb 4, 2022, estimated cost $370K, described as “Nycha boiler -amsterdam house- install new rooftop equipment dunnage as per plans. No change in use, egress or occupancy”
- Alteration, filed Feb 4, 2022, estimated cost $2.0M, described as “Nycha boiler - amsterdam house 4 - demolish existing steam fired hot water tank and associated piping. Provide all new heat pump hot water heater system for the existing building. No change in use, egress or occupancy.”
- Alteration, filed Sep 8, 2021, estimated cost $150K, described as “Nycha boiler - abandon existing buried fuel storage tank as per plans. No change in use, egress or occupancy.”
Property taxes
- Assessment
- $9,597,150
- Market value (city estimate)
- $21,327,000
- Taxable value
- $0
- Assessed land
- $900,000
- Assessed improvements
- $8,697,150
Zoning
R8 (part of the lot is R8B): floor area ratio 5.21 built, 6.02 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.