# 586 West 177th Street, Manhattan

Public School · built c. 1914 · Block 2133, Lot 40.

On Umarelli: https://umarelli.org/nyc/1021330040/586-west-177-street

More construction in Washington Heights: https://umarelli.org/nyc/manhattan/washington-heights.md

Every lot on block 2133: https://umarelli.org/nyc/manhattan/2133.md

## Building permits

- Alteration, filed Oct 21, 2026, estimated cost $20K, described as “Ch/PS115M- for temporary construction equipment (chute)submitting on behalf of contractor, related with DOB # M00703155, M00746644 .no change in use, occupancy or egress”
- Alteration, filed Oct 21, 2026, estimated cost $20K, described as “Sf/PS115M- for temporary construction equipment (scaffold)submitting on behalf of contractor, related with DOB # M00703155, M00746644 .no change in use, occupancy or egress”
- Alteration, filed Oct 21, 2026, estimated cost $20K, described as “Sh/PS115M- for temporary construction equipment (shed)submitting on behalf of contractor, related with DOB # M00703155, M00746644 .no change in use, occupancy or egress”
- Alteration, filed Oct 21, 2026, estimated cost $20K, described as “Fn/PS115M- for temporary construction equipment (fence)submitting on behalf of contractor, related with DOB # M00703155, M00746644 .no change in use, occupancy or egress”
- Alteration, filed Oct 8, 2024, estimated cost $34K, described as “Remove toilets/sinks/bathroom partitions/fixtures & install new accessible toilets/sinks with new partitions/fixtures/grab-bars. Install new mirrors/accessible mirror/accessible door hardware/ADA push button door. Remove/replace affected…”
- Alteration, filed Aug 9, 2024, estimated cost $146K, described as “Remove/replace existing floor,wall and ceiling finishes, remove existing partitions, provide door opening, non load bearing interior partitions, prove entrance/closet doors, patch, repair, paint affected partitions, provide two (2) 18"x18"…”
- Alteration, filed Jun 17, 2022, estimated cost $50K, described as “Remove and replace existing house keeping pads”
- Alteration, filed Jun 6, 2022, estimated cost $2.2M, described as “Remove and replace 3 existing heating and ventilation blowers in cellar and all related ductwork, remove, replace and install new ductwork for the auditorium and upper floors as per plans. no change in use, egress or occupancy under this…”
- Alteration, filed Mar 23, 2022, estimated cost $4.2M, described as “Patch, repair exterior masonry. Patch repair exist. plaster walls, ceiling in kind and repair. Window replacement including exterior/interior guards. Replace concrete pavers at sidewalks. water proofing at cellar, areaways. Replace toilet…”

## Property taxes

- Assessment: $8,552,250
- Market value (city estimate): $19,005,000
- Taxable value: $0
- Assessed land: $900,000
- Assessed improvements: $7,652,250

## Zoning

R7-2: floor area ratio 3.08 built, 3.44 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology