2522 Park Avenue, The Bronx
College · built 2023 · Block 2322, Lot 28.
Building permits
- New Building — Non-residential, filed Apr 1, 2022, estimated cost $117.0M, 7 stories, described as “Construct new seven (7) story school building as per plans filed.”
- Alteration, filed Jul 30, 2026, estimated cost $100K, described as “Install new cable supported ornamental flexible stainless steel wire mesh nets in existing stairwell "c". No change to the use, occupancy or egress is proposed under this application.”
- Alteration, filed Jun 15, 2026, estimated cost $3K, described as “Install exterior non-illuminated wall sign (kipp NYC)”
- Alteration, filed May 27, 2026, estimated cost $2K, described as “Install exterior non-illuminated wall sign (kipp NYC)”
- Alteration, filed Dec 2, 2025, estimated cost $5K, described as “Temporary pipe scaffold as per drawings. Scaffold shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Mar 19, 2025, described as “Installation of an adt access system as per plans. No change in use, egress or occupancy under this application. Scaffold to comply with chapter 33 of NYC building code of 2022.”
- Alteration, filed Dec 5, 2024, estimated cost $10K, described as “Install and use GBL workhorse material lifting crab.”
- Alteration, filed Oct 21, 2024, estimated cost $50K, described as “One (1) sypder mini-crane will be used for erection of curtain wall, screen wall, andglass box feature for 7-story building.”
- Alteration, filed Oct 15, 2024, estimated cost $5K, described as “Temporary work platform as per drawings. Work platform shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- No Work, filed May 2, 2024
- No Work, filed May 2, 2024
- No Work, filed May 2, 2024
- No Work, filed May 2, 2024
- Alteration, filed Apr 29, 2024, estimated cost $1K, described as “Installation of steel pipe scaffold as per plans. No change in egress, use, or occupancy.”
- Alteration, filed Apr 19, 2024, estimated cost $5K, described as “Temporary hoist run-back structure during new bldg construction, filed separately. Hoist run-back structure shall comply with ch #33 of the NYC bldg code. No change in use, occupancy or egress under this application. Hoist & elevator appl…”
- Alteration, filed Apr 19, 2024, estimated cost $20K, described as “Equipment use: dual 7000 # capacity personnel/material hoists during NB const, filed sep. Hoists shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application. Elevator application submitted separately”
- Alteration, filed Dec 21, 2023, estimated cost $5K, described as “Construction fence as per drawings during NB const, filed sep. Construction fence shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application. Dot permits by others for fence installed on…”
- Alteration, filed Dec 21, 2023, estimated cost $5K, described as “Heavy duty sidewalk shed during NB const, filed sep. Sidewalk shed shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application. Dot permits by others for shed installed on sidewalk/roadway”
- Alteration, filed Oct 5, 2022, described as “Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Oct 5, 2022, described as “Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Oct 5, 2022, described as “Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Jul 11, 2022, estimated cost $1K, described as “Install temporary dry standpipe system during construction as per plans filed. No change to use, egress, or occupancy. Filed in conjunction with NB#X00658182-I1”
- Alteration, filed May 3, 2022, estimated cost $5K, described as “Installation of 8' high temporary plywood construction fence”
Property taxes
- Assessment
- $252,450
- Market value (city estimate)
- $561,000
- Taxable value
- $0
- Assessed land
- $252,450
Tax breaks
- Nonprofit exemption (nonprofit, use planned), with no end date, about $27,386 a year below the full tax.
Zoning
M1-4/R7X: floor area ratio 4.76 built, 5.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, moderate risk: a 0.2% chance of flooding each year.
Recent sales
- May 27, 2021: $21,700,000
Open-market sales since 2016, from the Department of Finance’s sales files.
In the news
Foundations Take Shape for KIPP NYC Charter School at 75 Canal Street West in Mott Haven, The Bronx, New York YIMBY, Nov 28, 2023.