# 14 Mt Hope Place, The Bronx

Apartment building · 54 units · built c. 1910 · Block 2851, Lot 14.

On Umarelli: https://umarelli.org/nyc/2028510014/14-mt-hope-place

More construction in Mount Hope and Mount Eden: https://umarelli.org/nyc/bronx/mount-hope-and-mount-eden.md

## Building permits

- Alteration, filed May 29, 2026, estimated cost $9K, described as “Installation of pipe scaffolding as per plans. All equipment shall comply with ch #33 of the NYC code 2022. No change in use, occupancy or egress under this application.”
- Alteration, filed Dec 26, 2024, estimated cost $9K, described as “Installation of 300PSF sidewalk shed as per plans. All equipment shall comply with ch #33 of the NYC code 2022. No change in use, occupancy or egress under this application.”
- Major Renovation — Conversion, filed Oct 7, 2024, estimated cost $2.6M, 24 units added, 4 stories, described as “It is proposed to renovate the existing building, relocate community kitchen & add bathroom on each fl & eliminate the superintendents apartment. General construction, plumbing, mechanical & sprinkler work to be filed separately. See conh…”
- Alteration, filed Mar 29, 2024, estimated cost $17K, described as “Installation of pipe scaffolding & 300PSF heavy duty sidewalk shed as per plans. Temporary equipment shall comply with chapter #33 of the 2022 code. No change in use, egress or occupancy under this application.”
- Alteration, filed Mar 7, 2024, estimated cost $100K, described as “It is proposed to modify existing mechanical system as shown on plans. No change to use, egress or occupancy.”
- Alteration, filed Mar 7, 2024, estimated cost $104K, described as “It is proposed to modify existing sprinkler system as shown on plans. No change to use, egress, or occupancy. This application is filed in-conjunction with appl X00969989.”
- Alteration, filed Mar 7, 2024, estimated cost $29K, described as “It is proposed to file to install plumbing fixtures as shown on plans. No change to use, egress or occupancy.”
- Alteration, filed Dec 5, 2023, estimated cost $63K, described as “Proposed to restore community kitchens on basement, 1-4 fls & remove partitions between front rm & 2ND rm at 2ND & 3RD fls as per ecb violation 34957167Y. Make community kitchens & bathrooms handicap accessible. Paint, patch or replace…”

## Property taxes

- Assessment: $832,050
- 2026–27 tax: $101,304
- Market value (city estimate): $1,849,000
- Taxable value: $814,410
- Assessed land: $90,000
- Assessed improvements: $742,050

## Zoning

R8: floor area ratio 2.67 built, 6.02 allowed by base zoning.

## Recent sales

- May 27, 2026: $5,680,125, 16,685 sq ft ($340 per sq ft)
- Oct 31, 2023: $4,000,000

Open-market sales since 2016, from the Department of Finance’s sales files.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology