2540 Belmont Avenue, The Bronx
College · built c. 1931 · Block 3273, Lot 209.
Building permits
- Alteration, filed Sep 8, 2023, estimated cost $45K, described as “Remove and replace exist'g fireproofing on steel beams and metal decking.”
- Alteration, filed Jul 13, 2023, estimated cost $30K, described as “Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.”
- Alteration, filed Jun 28, 2023, estimated cost $899K, described as “Fmh emergency facade repairs.- entire west facade and partial south facade no change of use, egress occupancy.”
- Alteration, filed Apr 4, 2023, estimated cost $100K, described as “Installation of the required by the ConEd Gas meter Decorative Enclosure, no enlargement of the ZFA. No change of use, egress, or occupancy.”
- Alteration, filed Nov 30, 2021, estimated cost $180K, described as “Application is filed for the Existing pantry and restroom renovation on the 005FL at the Faculty Memorial Hall (FMH). No change of use, egress or occupancy.”
- Alteration, filed Nov 29, 2021, estimated cost $1.0M, described as “Application is filed for the interior renovation of Room 131 at the FMH. No change of use, egress or occupancy.”
- Alteration, filed Oct 6, 2021, estimated cost $7K, described as “Installation of temporary scaffold as per drawings. Scaffold shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Sep 7, 2021, estimated cost $15K, described as “Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application”
- Alteration, filed Jul 19, 2021, estimated cost $250K, described as “Application is filed for the boiler room construction on the Cellar Level of the Faculty Memorial Hall. No change of use, egress or occupancy.”
- Alteration, filed May 28, 2021, estimated cost $65K, described as “Replacement of the railings on the 2nd floor roof at Faculty Memorial Hall (FMH). No change of use, egress or occupancy.”
- Alteration, filed Mar 3, 2020, estimated cost $5K, described as “Steel and concrete for support of HVAC equipment”
- Alteration, filed Dec 23, 2019, estimated cost $50K, described as “Plumbing work associated with 2nd floor offices renovation within Faculty Memorial Hall including removal of 3WC, 2LAV; replacement of 1 DF; installation of 2 new SINKS , 1 new DF and a associated piping. No change of use, egress or…”
- Alteration, filed Dec 23, 2019, estimated cost $520K, described as “Mechanical work associated with 2nd floor offices renovation at FMH (Faculty Memorial Hall) building including installation of new split system. No change of use, egress or occupancy.”
Building history
- Alteration, filed Oct 25, 1990, signed off Jan 24, 1997, described as “Legalize change from a manufacturing bld g. To a fordham university educational and accessory administrative facily use and occ all work was completed under the jurisdiction of of t he the nys dormitory authority and is tax expemted”
New buildings, demolitions and major alterations filed in the city’s older system since 1989.
Property taxes
- Assessment
- $7,007,850
- Market value (city estimate)
- $15,573,000
- Taxable value
- $0
- Assessed land
- $330,750
- Assessed improvements
- $6,677,100
Tax breaks
- Nonprofit exemption (college or university), with no end date, about $760,212 a year below the full tax.
Zoning
C4-5D: floor area ratio 1.92 built, 4.66 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- FORDHAM UNIVERSITY PKG GARAGE (City Planning P2003X0279): Completed, decided Aug 25, 2003. REZONE C8-1 & R6 TO R6/C2-3 FOR A 150 PUBLIC PARKING IN*EXECSS OF 150 SPACES