# 120 3rd Avenue, Brooklyn

Apartment building · 709 units · built 1965 · Block 394, Lot 1.

On Umarelli: https://umarelli.org/nyc/3003940001/120-3-avenue

More construction in Boerum Hill: https://umarelli.org/nyc/brooklyn/boerum-hill.md

Every lot on block 394: https://umarelli.org/nyc/brooklyn/394.md

## Building permits

- Alteration, filed May 1, 2026, estimated cost $1.6M, described as “Demolition of existing concrete walls, curb & pavement, 5. Removal of existing light poles. And supply and installation of new modified shipping containers.”
- Alteration, filed Sep 19, 2025, described as “Outriggers system installation for facade repairs, no change in use, egress, or occupancy.”
- Alteration, filed Sep 19, 2025, estimated cost $50K, described as “Installation of supported pipe scaffold as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Sep 16, 2025, estimated cost $33K, described as “Installation of temporary construction chain link fence. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 19, 2025, estimated cost $13K, described as “Installation of temporary construction chain link fence. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 18, 2025, estimated cost $13K, described as “Installation of temporary construction chain link fence. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 18, 2025, estimated cost $16K, described as “Installation of temporary construction chain link fence. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 7, 2025, estimated cost $16K, described as “Installation of temporary construction chain link fence. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 7, 2025, estimated cost $13K, described as “Installation of temporary construction chain link fence. No change in use, egress or occupancy under this application.”
- Alteration, filed Aug 6, 2025, estimated cost $100K, described as “Installation of new sidewalk shed as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Aug 6, 2025, estimated cost $84K, described as “Installation of new sidewalk shed as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Aug 6, 2025, estimated cost $40K, described as “Installation of new sidewalk shed as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Jul 15, 2025, estimated cost $6.3M, described as “NYCHA/Wyckoff/ Bldg#1- Proposed Architectural scope filed for replacement of all apartment kitchens and bathrooms, conversion of units for section 504 compliance and the re-cladding of existing canopies. All as per plans filed herewith.”
- Alteration, filed Jul 15, 2025, estimated cost $6.3M, described as “NYCHA/Wyckoff/ Bldg#2- Proposed Architectural scope filed for replacement of apartment kitchens and bathrooms and the re-cladding of existing canopies. All as per plans filed herewith.”
- Alteration, filed Jul 15, 2025, estimated cost $6.5M, described as “NYCHA/Wyckoff/ Bldg#3- Proposed Arch. scope filed for replacement of apt. kitchens and bathrooms, conversion of units for section 504 compliance & re-cladding of existing canopies. All as per plans filed herewith.”
- Alteration, filed Mar 10, 2025, described as “FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola”
- Alteration, filed Mar 10, 2025, described as “FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola”
- Alteration, filed Mar 10, 2025, described as “FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola”
- Alteration, filed Feb 27, 2025, estimated cost $10K, described as “Installation of temporary construction fence as indicated on plans. No change in use, egress, or occupancy.”
- Alteration, filed Feb 27, 2025, estimated cost $35K, described as “To provide shoring and sheeting for on going construction on an open space. No exterior work on building will be performed under this application. Structural stability will not be affected. No change in use, egress or occupancy.”
- Alteration, filed Sep 17, 2024, estimated cost $50K, described as “Installation of temporary construction shoring for excavation at 272 wyckoff street, brooklyn as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Jul 23, 2024, estimated cost $10K, described as “Installation of temporary construction fence at 272 wyckoff street, brooklyn as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Oct 24, 2023, estimated cost $3.0M, described as “Single story addition connected to the existing community center as shown in the contract documents, at the followingaddress: 272 wyckoff street, brooklyn, new york, 11217.”
- Alteration, filed Oct 13, 2023, estimated cost $3.0M, described as “The scope of work includes but is not limited to the construction of new steel framestructure and 8" hollow core slab for the addition of community center. Also includes the construction of frame structure for the security fence for the…”
- Alteration, filed Sep 28, 2023, estimated cost $77K, described as “Replacing existing "F" gas riser for cooking only from cellar to the 14th floor as per plans filed herewith.”

3 more, older permits are in this building’s full list on the map: https://umarelli.org/nyc/3003940001/120-3-avenue.

## Property taxes

- Assessment: $29,179,800
- Market value (city estimate): $64,844,000
- Taxable value: $0
- Assessed land: $2,700,000
- Assessed improvements: $26,479,800

## Zoning

R6: floor area ratio 2.10 built, 2.43 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology