80 Crown Street, Brooklyn
College · built 1987 · Block 1294, Lot 1.
Building permits
- Alteration, filed Jan 22, 2026, estimated cost $1.3M, described as “Filing for general construction associated with the demolition and reconstruction of the existing courtyard at Medgar Evers College (CUNY), including a new steel-framed fabric canopy, handrails, ramps, and raised platforms per plans.”
- Alteration, filed Jan 20, 2026, estimated cost $150K, described as “Installation of structural work for emergency generator. See plans for detail. No change of use, egress or occupancy under this application”
- Alteration, filed Jan 20, 2026, estimated cost $2.3M, described as “Installation of emergency generator with related mechanical equipment. Removal of abandoned boiler equipment. No change of use, egress or occupancy”
- Alteration, filed Jul 14, 2021, estimated cost $370K, described as “Structural modifications”
- Alteration, filed Mar 26, 2021, estimated cost $414K, described as “Plumbing modifications as indicated on plans filed herewith. Sprinkler modifications as indicated on plans filed herewith. No change in use, egress or occupancy”
- Alteration, filed Mar 19, 2021, estimated cost $405K, described as “Plumbing modifications as indicated on plans filed herewith. No change in use, egress or occupancy”
- Alteration, filed Mar 19, 2021, estimated cost $335K, described as “Mechanical modifications as indicated on plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Mar 19, 2021, estimated cost $9K, described as “Sprinkler modifications as indicated on plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Jul 6, 2020, estimated cost $10K, described as “Installation of temporary construction fence at 1650 bedford avenue, brooklyn as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- No Work, filed Jul 3, 2019
Property taxes
- Assessment
- $18,379,350
- Market value (city estimate)
- $40,843,000
- Taxable value
- $0
- Assessed land
- $1,944,450
- Assessed improvements
- $16,434,900
Zoning
R6 (part of the lot is R6A): floor area ratio 0.81 built, 2.43 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- CROWN STREET (City Planning P2009K0034): Completed, decided Oct 12, 2011. DEMAP A 1 BLOCK SEGMENT OF CROWN ST TO CREATE A MEDGAR EVERS*COLLEGE CAMPUS COMMON AREA
- 175 MONTGOMERY ST (City Planning P1984K0244): Completed, decided Dec 28, 1983. DISPOSITION OF CITY-OWNED PROPERTY, 1 PARCEL