Condominium · 13 units · built 1956 · Block 2003, Lot 7502.
Building permits
- Alteration, filed Oct 9, 2026, estimated cost $30K, described as “Existing electric unit (5) steam heaters to be replaced in mechanical room on floors 1-4 no change to use, egress or occupancy under this application.”
- Alteration, filed Jun 26, 2025, described as “Installation of suspended scaffold for facade inspection/ repair.”
- No Work, filed Aug 12, 2024
- Alteration, filed Jul 18, 2024, described as “Installation of temporary pipe scaffold as per plans. No change in use, egress or occupancy.”
- Alteration, filed Jun 6, 2024, described as “Installation of suspended scaffold for facade inspection/repair.”
- Alteration, filed Aug 11, 2023, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Jul 17, 2023, estimated cost $10K, described as “Filing for the installation of a new fuel storage tank associated with new emergency generator filed under B00829899-I1. No change of use, occupancy, or egress.”
- Alteration, filed Jul 17, 2023, estimated cost $20K, described as “Filing for installation of a new emergency generator on the ground in conjunction with B00829904-I1. No change in use, occupancy, or egress.”
- Alteration, filed Apr 28, 2023, estimated cost $25K, described as “Application filed to record egress easement and exterior stair between 62 hanson- lot 20 and 68 hanson- vacant lot 29”
- Alteration, filed Jul 31, 2022, estimated cost $500K, described as “Alt-co filed for change of use on floors 12 & 13 of existing public facility and to update pa space on 3RD floor. New certificate of occupancy to be obtained.”
- Alteration, filed Apr 22, 2022, estimated cost $168K, described as “Sprinkler work filed in conjunction with renovation of existing public building. No change in use, occupancy, or egress.”
- Alteration, filed Apr 22, 2022, estimated cost $175K, described as “Plumbing work filed in conjunction with renovation of existing public facility. No change in use, occupancy, or egress.”
- Alteration, filed Apr 22, 2022, estimated cost $350K, described as “Mechanical work filed in conjunction with renovation of existing public facility. No change in use, occupancy, or egress.”
- Alteration, filed Apr 12, 2022, estimated cost $2.0M, described as “Gc work filed to renovate existing community facility building. No change in use, occupancy, or egress.”
- Alteration, filed Apr 11, 2022, estimated cost $300K, described as “Structural work filed to remove bulkhead on 4TH floor roof and infill. No change in use, occupancy, or egress.”
- Alteration, filed Sep 3, 2020, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy.sidewalk shed shall comply with chapter #33 of the NYC building code.live load 300PSF.”
- Alteration, filed Apr 23, 2019, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy.sidewalk shed shall comply with chapter #33 of the NYC building code.live load 300PSF.”
Property taxes
- Assessment
- $5,065,700
- 2026–27 tax
- $544,019
- Market value (city estimate)
- $11,257,111
- Taxable value
- $4,659,965
- Assessed land
- $361,400
- Assessed improvements
- $4,704,300
- Condo units with their own tax lots
- 2
Zoning
R7A: floor area ratio 3.08 built, 4.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.