# 49 Little Street, Brooklyn

Utility · Block 2023, Lot 125.

Some of the city’s records for this lot were still loading when this page was made; it refreshes within minutes.

On Umarelli: https://umarelli.org/nyc/3020230125/49-little-street

More construction in Bedford-Stuyvesant: https://umarelli.org/nyc/brooklyn/bedford-stuyvesant.md

Every lot on block 2023: https://umarelli.org/nyc/brooklyn/2023.md

## Building permits

- Alteration, filed Dec 19, 2025, estimated cost $11.1M, described as “Reconstruction of the main sewage pump system - redhook wastewater resource recovery facility rh-83-des, structural work.”
- Alteration, filed Dec 18, 2025, estimated cost $122.8M, described as “Reconstruction of the main sewage pump system -redhook wastewater resource recovery facilityrh-83-des. I1 submission for general construction.”
- Alteration, filed Jul 28, 2025, estimated cost $374K, described as “RLCY-RH-03-J20G-F-02 To replace existing truck scale load cells, elevate control panel, and install waterproof accessways at Red Hook wastewater facility.”
- Alteration, filed Jul 28, 2025, estimated cost $1.3M, described as “RLCY-RH-02-J20G-F-01 To restore/replace electrical conduit, wire, systems, and replacement of light poles at Red Hook wastewater treatment facility”
- Alteration, filed Oct 12, 2021, estimated cost $205K, described as “Remove and replace four (4) existing sump pumps in kind. Remove and replace associated piping, connections, and valve materials. No change to occupancy, use, or egress under this application.”
- Alteration, filed Oct 12, 2021, estimated cost $205K, described as “Remove and replace four (4) existing sump pumps in kind. Remove and replace associated piping, connections, and valve materials. No change to occupancy, use or egress under this application.”
- Alteration, filed Oct 12, 2021, estimated cost $211K, described as “Remove and replace four (4) existing pumps. Remove and replace associated piping, connections, and valve materials. Install post installed anchors. No change to occupancy, use, or egress under this application.”
- Alteration, filed Oct 12, 2021, estimated cost $218K, described as “Remove and replace four (4) existing pumps. Remove and replace associated piping, connections, and valve materials. No change to occupancy, use or egress under this application.”
- Alteration, filed Oct 12, 2021, estimated cost $781K, described as “Remove and replace sixteen (16) existing sump pumps. Remove and replace suction, discharge pipes, and seal water and ball valves. Install post installed anchors. No change to occupancy, use or egress under this application.”
- Alteration, filed Apr 17, 2020, estimated cost $650K, described as “Removal and replacement of eight (8) process sump pumps and associated piping”
- Alteration, filed Apr 17, 2020, estimated cost $587K, described as “Removal and replacement of five (5) process sump pumps and one (1) sewage ejector pump set. Remove and replace sanitary vent and install backwater valve.”
- Alteration, filed Apr 17, 2020, estimated cost $650K, described as “Removal and replacement of eight (8) process sump pumps and associated piping.”
- Alteration, filed Apr 17, 2020, estimated cost $1.3M, described as “Remove and replace three service water pumps, three seal water pumps, one sewage ejector set. Install one backwater valve on a sanitary discharge pipe and one gate valve on a drain pipe.”
- Alteration, filed Apr 17, 2020, estimated cost $779K, described as “Removal and replacement of four (4) process sump pumps and associated piping.”
- Alteration, filed Apr 17, 2020, estimated cost $449K, described as “Removal and replacement of six (6) process sump pumps and associated piping; removal and replacement of sanitary vent and installation of backwater valve.”
- Alteration, filed Apr 17, 2020, estimated cost $1.3M, described as “Filing for the removal and replacement of six grit suspension pumps and two process sump pumps and associated piping replacements. Pumps are located in basement of the Aeration and Primary Settling Tanks. No change in use, egress or…”
- Alteration, filed Apr 17, 2020, estimated cost $1.2M, described as “Filing for the removal and replacement of sixteen (16) process sump pumps and associated piping replacements. No change in use, egress occupancy under this application”

## Zoning

M3-1: floor area ratio 0.00 built, 2.00 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, moderate risk: a 0.2% chance of flooding each year.

From New York City and Jersey City public records, refreshed within a day of each release. Sources: https://umarelli.org/sources. Methodology and corrections: https://umarelli.org/methodology