## Building permits

- Alteration, filed Jan 8, 2026, estimated cost $844K, described as “Exterior facade repairs per plans: Repair/Removal/replacement of cracked & spalled masonry & stucco, metal copings, steel lintels, spandrel beams, parapets and exterior door. Masonry repointing. Scraping & painting of steel lintels &…”
- Alteration, filed Apr 23, 2024, estimated cost $10K, described as “Construction of an 8 ft high fence In front of the side walkway to repair the existing retaining wall as per plan no change use, egress and occupancy.”
- Alteration, filed Feb 13, 2024, described as “Installation of heavy duty sidewalk shed. no change in use, occupancy or egress. work shall comply with chapter 33 of nycc.”
- Alteration, filed Feb 7, 2024, described as “Installation of heavy duty sidewalk shed. no change in use, occupancy or egress. work shall comply with chapter 33 of nycc.”
- Alteration, filed Jan 19, 2024, estimated cost $40K, described as “Reconstruction of existing damaged retaining wall as per plan. No change in use, egress or occupancy.”
- Alteration, filed Jan 20, 2022, estimated cost $550, described as “Illuminated non advertising accessory sign on existing hospital entrance marquee - in property lines - emergency. No change of use, egress or occupancy.”
- Alteration, filed Jan 20, 2022, estimated cost $550, described as “Illuminated non advertising accessory sign - in property lines - ambulance. No change of use, egress or occupancy.”
- Alteration, filed Jan 20, 2022, estimated cost $600, described as “Illuminated double sided non advertising accessory ground sign on existing concrete pad - in property lines - emergency the brooklyn hospital center. No change of use, egress or occupancy.”
- Alteration, filed Jan 20, 2022, estimated cost $1K, described as “Non illuminated non advertising accessory sign - in property lnes - frank coleman hamm, m.d. Entrance. No change of use, egress or occupancy.”
- Alteration, filed Apr 29, 2021, estimated cost $80K, described as “Replacement and installation of exhaust duct and fan for existing kitchen. No change in use, occupancy and means of egress is involved under this application.”
- Alteration, filed Apr 9, 2021, estimated cost $12K, described as “Installation of temporary overhead protection during building alt, filed sep. Temporary overhead protection shall comply with ch #33 of the NYC bc. No change in use, occupancy or egress under this application.”
- Alteration, filed Apr 9, 2021, estimated cost $10K, described as “Installation of temporary fence on top of yodock barriers as per drawings. Fence shall comply with chapter #33 of the NYC building code. No change in use, occupancy or egress under this application.”
- Alteration, filed Jul 21, 2020, estimated cost $5K, described as “Tbhc - ortho space - modifications to existing sprinkler system as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Jul 8, 2020, estimated cost $44K, described as “Tbhs - department of medicine relocation - modifications to the existing sprinkler system. No change in use, egress, or occupancy.”
- Alteration, filed Jul 8, 2020, estimated cost $29K, described as “Tbhs - department of medicine relocation - plumbing modifications as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Jun 8, 2020, estimated cost $19K, described as “Tbhs - pre-admission testing - modifications to the existing sprinkler system as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Jun 8, 2020, estimated cost $13K, described as “The brooklyn hospital center - pre-admission testing - plumbing modifications as indicated on plans filed herewith. No change in use, egress or occupancy.”
- Alteration, filed Nov 26, 2019, estimated cost $50K, described as “Herewith filing sprinkler work for brooklyn hospital center. Scope includes the modification of exiting sprinkler system. No change in use, egress or occupancy filed under this application.”
- Alteration, filed Nov 26, 2019, estimated cost $50K, described as “Herewith filing plumbing work for brooklyn hospital center; family medicine bdgl. Scope includes the removal of 1 existing toilet and hand sink and installation of new plumbing fixtures. No change in use, egress or occupancy filed under…”
- Alteration, filed Nov 26, 2019, estimated cost $200K, described as “Herewith filing mechanical work for brooklyn hospital center; family medicine bdgl. Scope includes installation of new mechanical equipment for heating and cooling. No change in use, egress or occupancy filed under this application.”
- Alteration, filed Apr 12, 2019, estimated cost $5K, described as “Erect, maintain and dismantle heavy duty sidewalk shed as per plans filed herewith. no change to use, egress or occupancy.”

## Property taxes

- Assessment: $60,318,450
- Market value (city estimate): $134,041,000
- Taxable value: $0
- Assessed land: $2,477,700
- Assessed improvements: $57,840,750

## Tax breaks

- Nonprofit exemption (hospital), with no end date, about $6,543,345 a year below the full tax.

## Zoning

R6: floor area ratio 1.95 built, 2.43 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.

## Board and land use applications

- BKLYN HOSPITAL AMBULANCE STATION (City Planning P1997K0468): Completed, decided Oct 31, 1997. 97CFD002K: DEVELOPMENT OF A FIRE DEPT. BUREAU OF EMERGENCY MEDICAL SERV ICE AMBULANCE STATION IN A PORTIN OF A HOSPITAL PARKING LOT ACROSS THE STREET FROM BROOKLYN HOSPITAL