65 Roebling Street, Brooklyn
Apartment Building · 24 units · built c. 1910 · Block 2322, Lot 6.
Building permits
- Alteration, filed Jul 28, 2026, estimated cost $5K, described as “Installation of temporary plywood construction fence”
- Alteration, filed Jun 9, 2026, estimated cost $35K, described as “Plumbing modifications to take place on the cellar floor, first floor through 2nd floor as per drawings filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed May 15, 2026, estimated cost $2.8M, described as “General Construction to take place on the first floor through third floor. as per plans filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Jan 29, 2026, estimated cost $1K, described as “Installation of temporary heavy duty sidewalk shed as per plans. No change in use, egress or occupancy. Sidewalk shed shall comply with chapter #33 of 2022 the NYC building code. Live load 300PSF.”
- Alteration, filed Jan 29, 2026, estimated cost $1K, described as “Installation of temporary barrier as per plans. No change in use, egress or occupancy shall comply with CHAPTER#33 of 2022 the ny building code.”
- Alteration, filed Jan 29, 2026, estimated cost $1K, described as “Proposed installation of temporary pipe scaffold as per plans. Work shall comply with chapter #33 of 2022 the NYC building code. No change in use, occupancy, or egress under this application.”
- Alteration, filed Oct 15, 2025, estimated cost $959K, described as “Plumbing modifications to take place on the first through third floor as per drawings filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Oct 15, 2025, estimated cost $266K, described as “Sprinkler & Standpipe modifications to take place on the first through third floor as per drawings filed herewith. No change in use, egress, or occupancy.”
- Alteration, filed Mar 21, 2025, estimated cost $365K, described as “Mechanical work in conjunction w/ interior reno. Upgrade of heating system; new condensing boilers - heating hot water & domestic hot water. New radiators installed in each Apt; updated piping, equipment locations & connection details.”
- Alteration, filed Mar 21, 2025, estimated cost $329K, described as “New Boiler install to take place on the roof as per plans filed herewith. No change in use, egress, or occupancy.,”
- Alteration, filed Mar 13, 2025, estimated cost $86K, described as “Structural modifications to take place on all floors as per plans filed herewith.”
- Alteration, filed Mar 13, 2025, estimated cost $43K, described as “Relocation of exterior wall to accomodate legalization of existing imd units and proposal of new residential units. Approx. Work area: 450 sq. Ft.”
- Alteration, filed Mar 12, 2024, estimated cost $127K, described as “Sprinkler work in entire building as reflected on plans”
Property taxes
- Assessment
- $1,875,600
- 2026–27 Tax
- $220,006
- Market value (city estimate)
- $4,168,000
- Taxable value
- $1,768,680
- Assessed land
- $253,350
- Assessed improvements
- $1,622,250
Zoning
M1-2/R6A: floor area ratio 2.56 built, 3.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, moderate risk: a 0.2% chance of flooding each year. FEMA’s preliminary map: zone X, minimal flood hazard.
Recent sales
- Oct 13, 2022: $7,000,000
Open-market sales since 2016, from the Department of Finance’s sales files.