62 South 2nd Street, Brooklyn
Condominium · 29 units · built 1952 · Block 2415, Lot 7503.
Building permits
- Alteration, filed Aug 12, 2026, estimated cost $65K, described as “Sprinkler work in conjunction with interior renovation of commercial space”
- Alteration, filed Mar 26, 2026, estimated cost $400K, described as “Interior renovation of commercial space”
- Alteration, filed Mar 18, 2025, estimated cost $170K, described as “Built out of an existing restaurant. no change in use, egress and occupancy.”
- Alteration, filed Jan 6, 2025, estimated cost $18K, described as “Soft Demolition of an existing restaurant. no change in use, egress and occupancy.”
- Alteration, filed Mar 29, 2024, estimated cost $925, described as “Erect non-illuminated accessory business wall sign; copy reading "industrious"”
- Alteration, filed Mar 29, 2024, estimated cost $650, described as “Erect non-illuminated double-faced projecting accessory business sign; copy reading "industrious"”
- Alteration, filed Mar 15, 2024, estimated cost $125K, described as “Application filed for the installation of non-loadbearing partitions, doors and related finishes, as per plans. No change in use, egress, occupancy or bulk.”
- Major Renovation — Multi-Family, filed Sep 21, 2023, 28 units in all, 5 stories, described as “Increase occupant load on the 3rd floor for office use. Combine the schedule of occupancy into a single line for a single tenant”
- Alteration, filed Sep 20, 2023, estimated cost $1.1M, described as “Construct interior partitions, ceilings and doors on 3rd floor as shown.”
- Alteration, filed Sep 19, 2023, estimated cost $50K, described as “Modification to plumbing fixtures and related piping on 3rd floor”
- Alteration, filed Sep 19, 2023, estimated cost $220K, described as “Modification to sprinkler heads and related piping on 3rd floor.”
- Alteration, filed Sep 19, 2023, estimated cost $468K, described as “Modifications and relocation of mechanical ductwork, fan coils, ventilation and condensation pipings to existing as per plans.”
- Alteration, filed Aug 22, 2023, estimated cost $1K, described as “Propose to install non-advertising sign. No change in use, egress, or occupancy.”
- Alteration, filed Aug 22, 2023, estimated cost $1K, described as “Propose to install non-advertising sign. No change in use, egress, or occupancy.”
- Alteration, filed Aug 22, 2023, estimated cost $1K, described as “Propose to install non-advertising sign. No change in use, egress, or occupancy,”
- Alteration, filed Jun 15, 2023, estimated cost $11K, described as “Removal and installation of sprinkler heads on exisitng sprinkler system as per plans filed herewith.”
- Alteration, filed Jun 15, 2023, estimated cost $20K, described as “Plumbing work on cellar and 1ST floor as per plans filed herewith. Filed in conjunction with general construction application B00888003. No change to use, egress or occupancy.”
- Alteration, filed Jun 15, 2023, estimated cost $50K, described as “Installation of HVAC units and realted duct work as per plans filed herewtih. Filed in conjunction with general construction application B00888003. No change to use, egress or occupancy”
- Alteration, filed Jun 14, 2023, estimated cost $50K, described as “Structural work as per plans filed herewith. Filed in conjunction to general construction application B00888003.”
- Alteration, filed Jun 13, 2023, estimated cost $569K, described as “Construction of interior non-bearing walls, doors and lighting, and new electrical outlets for new equipment. The scope also includes site work to repaint parking stalls and add electric charging stations. MEP, sprinkler and structural…”
- Alteration, filed Mar 1, 2023, estimated cost $427K, described as “Installation of HVAC units and realted duct work as per plans filed herewtih. Filed in conjunction with general construction application B08054859. No change to use, egress or occupancy.”
- Alteration, filed Mar 1, 2023, estimated cost $25K, described as “Structural work as per plans filed herewith. Filed in conjunction to general construction application B08054859.”
- Alteration, filed Mar 1, 2023, estimated cost $1.8M, described as “Core and shell updates to an existing building limited to the 20,686 sf tenant space at the ground level and the cellar. Modifications include replacement of exterior storefront glazing panels, addition of folding storefront doors, and new…”
- Alteration, filed Mar 1, 2023, estimated cost $137K, described as “Plumbing work on cellar and 1ST floor as per plans filed herewith. Filed in conjunction with general construction application B08054859. No change to use, egress or occupancy.”
- Alteration, filed Mar 1, 2023, estimated cost $29K, described as “Removal and installation of sprinkler heads on exisitng sprinkler system as per plans filed herewith.”
17 more, older permits are in this building’s full list on the map.
Property taxes
- Assessment
- $12,720,150
- 2026–27 tax
- $755,904
- Market value (city estimate)
- $28,267,000
- Taxable value
- $10,587,177
- Assessed land
- $1,170,450
- Assessed improvements
- $11,549,700
- Condo units with their own tax lots
- 2
Zoning
M1-4/R6A: floor area ratio 2.99 built, 3.00 allowed by base zoning.
Flood zone
Current FEMA flood map: zone X, minimal flood hazard.
Board and land use applications
- Variance or special permit (Board of Standards and Appeals 2020-12-BZ): Variance or special permit, Granted, filed Feb 19, 2020, decided Jan 28, 2021. Special Permit (§73-36) to permit the operation of a physical cultural establishment (Row House Williamsburg) located in the cellar and a portion of the first floor of an existing building contrary to ZR §42-10. M1-4/R6-A & MX-8 zoning…