## Building permits

- Alteration, filed Apr 12, 2024, estimated cost $37K, described as “Demo portion of existing wall between rooms 211 and 213 and existing cabinetry. Install a new sliding glass door between room 211 and 213. Install new sink and mill-work in rooms 211 and 213. Patch existing finishes as needed.”
- Alteration, filed Nov 4, 2023, estimated cost $30K, described as “Installation of temporary construction shoring for excavation as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Oct 13, 2023, estimated cost $20K, described as “Installation of debris chute for ps 19K at 325 south 3 street, brooklyn as per indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Oct 13, 2023, estimated cost $30K, described as “Installation of pipe scaffold for ps 414K/ps 19K at 325 south 3 street, brooklyn as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Oct 12, 2023, estimated cost $20K, described as “Installation of new sidewalk shed for ps 19K at 325 south 3 street, brooklyn as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Oct 12, 2023, estimated cost $20K, described as “Installation of temporary construction fence for ps 19K at 325 south 3 street, brooklyn as indicated on plans. There will be no change in the use, egress, or occupancy under this application.”
- Alteration, filed Mar 8, 2023, estimated cost $1.0M, described as “K019-playground upgrade to include replacing asphalt, new steps & railing along with new fence & gate.”
- Alteration, filed Oct 5, 2022, estimated cost $5.3M, described as “K019 @ PS 414K : Repair of Ramps, main Entrance,, Fence & gate; replace Concrete & Asphalt pavement; repair of Reinf. Concrete Floors, Ceilings, walls; Remove, replace Masonry, Concrete and Lime Stones, Parapet walls & Roof work; replace…”
- Alteration, filed Aug 19, 2022, estimated cost $1.0M, described as “Emergency Structural work including demo of existing cmu wall & rebuilding of block wall, new steel brace, & vertical control joints & existing wall crack stitching.”

## Property taxes

- Assessment: $3,159,450
- Market value (city estimate): $7,021,000
- Taxable value: $0
- Assessed land: $738,000
- Assessed improvements: $2,421,450

## Zoning

R6: floor area ratio 0.68 built, 2.43 allowed by base zoning.

## Flood zone

Current FEMA flood map: zone X, minimal flood hazard.